Doubtnut Promotions Sticky

When A alone does a piece of work , he takes 25 days more than the time taken (A+B) to completes that particular work, while B alone takes 49 days more than the time taken by (A + B) to finish the same work. A andBtogether will take what time to finish this work?

A

35 days

B

25 days

C

15 days

D

45 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we need to first define the variables and understand the relationships given in the question.

Step 1: Define the Variables
Let:
- x = the number of days taken by A and B together to complete the work.
- A = the number of days taken by A alone to complete the work.
- B = the number of days taken by B alone to complete the work.

From the problem, we know:
- A=x+25 (A takes 25 days more than A and B together)
- B=x+49 (B takes 49 days more than A and B together)

Step 2: Use the Work Formula
The work done by A and B together can be expressed in terms of their individual work rates. The work done in one day by A is 1A and by B is 1B. Therefore, the work done by A and B together in one day is:
1A+1B=1x

Step 3: Substitute A and B
Substituting the expressions for A and B from Step 1 into the equation:
1x+25+1x+49=1x

Step 4: Find a Common Denominator
To solve the equation, we will find a common denominator for the left-hand side:
(x+49)+(x+25)(x+25)(x+49)=1x
This simplifies to:
2x+74(x+25)(x+49)=1x

Step 5: Cross Multiply
Cross multiplying gives us:
(2x+74)x=(x+25)(x+49)

Step 6: Expand Both Sides
Expanding both sides:
2x2+74x=x2+74x+1225

Step 7: Simplify the Equation
Subtract x2+74x+1225 from both sides:
2x2+74xx274x1225=0
This simplifies to:
x21225=0

Step 8: Solve for x
Factoring gives:
(x35)(x+35)=0
Thus, x=35 (we discard the negative solution as time cannot be negative).

Conclusion
A and B together will take 35 days to finish the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
    X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?

    A30 days
    B27 days
    C20 days
    D25 days
  • Question 2 - Select One

    A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?

    A4
    B2
    C12
    D16
  • Question 3 - Select One

    The complete a work, A takes 50 % more time than B. If together they takes 18 days to do complete the work, then B takes the time to do the work in :

    A30 days
    B35 dyas
    C40 days
    D45 days