A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for Rs. 5400. They begin the work together but B left 2 days before the completion of work and c left 5 days before the completion of work. The share of A from the assured money is

A

Rs.2700

B

Rs. 540

C

Rs. 1800

D

Rs. 600

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will follow the outlined approach in the video transcript.

Step 1: Determine the Work Rates of A, B, and C
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 24 days, so B's work rate is 124 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.

Step 2: Find the Total Work
To find a common measure for the work done, we can take the least common multiple (LCM) of the days:
- The LCM of 20, 24, and 30 is 120.
- Therefore, the total work can be assumed to be 120 units.

Step 3: Calculate Individual Work Contributions
Now, we calculate the work done by each person in terms of units:
- A's work in 120 units: 12020=6 units per day.
- B's work in 120 units: 12024=5 units per day.
- C's work in 120 units: 12030=4 units per day.

Step 4: Calculate Total Work Done Together
The combined work done by A, B, and C in one day is:
- Total work rate = 6+5+4=15 units per day.

Step 5: Determine the Total Time Worked
Let’s assume they worked together for x days. Since B left 2 days before the completion and C left 5 days before the completion, we can express the total work done as:
- A worked for x days.
- B worked for x2 days.
- C worked for x5 days.

The total work can be expressed as:
6x+5(x2)+4(x5)=120

Step 6: Simplify the Equation
Expanding the equation:
6x+5x10+4x20=120
Combining like terms:
15x30=120
Adding 30 to both sides:
15x=150
Dividing by 15:
x=10

Step 7: Calculate Work Done by Each Person
Now we can calculate how much work each person did:
- A's work: 6×10=60 units.
- B's work: 5×8=40 units (B worked for 8 days).
- C's work: 4×5=20 units (C worked for 5 days).

Step 8: Calculate the Share of A
The total work is 120 units, and the payment is Rs. 5400. The share of A can be calculated as follows:
Share of A=Work done by ATotal work×Total payment
Share of A=60120×5400=12×5400=2700

Final Answer
Thus, the share of A from the assured money is Rs. 2700.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?

    A7
    B10
    C12
    D9
  • A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these