A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for Rs. 5400. They begin the work together but B left 2 days before the completion of work and c left 5 days before the completion of work. The share of A from the assured money is
Rs.2700
Rs. 540
Rs. 1800
Rs. 600
The correct Answer is:A
To solve the problem step by step, we will follow the outlined approach in the video transcript.
Step 1: Determine the Work Rates of A, B, and C
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 24 days, so B's work rate is 124 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.
Step 2: Find the Total Work
To find a common measure for the work done, we can take the least common multiple (LCM) of the days:
- The LCM of 20, 24, and 30 is 120.
- Therefore, the total work can be assumed to be 120 units.
Step 3: Calculate Individual Work Contributions
Now, we calculate the work done by each person in terms of units:
- A's work in 120 units: 12020=6 units per day.
- B's work in 120 units: 12024=5 units per day.
- C's work in 120 units: 12030=4 units per day.
Step 4: Calculate Total Work Done Together
The combined work done by A, B, and C in one day is:
- Total work rate = 6+5+4=15 units per day.
Step 5: Determine the Total Time Worked
Let’s assume they worked together for x days. Since B left 2 days before the completion and C left 5 days before the completion, we can express the total work done as:
- A worked for x days.
- B worked for x−2 days.
- C worked for x−5 days.
The total work can be expressed as:
6x+5(x−2)+4(x−5)=120
Step 6: Simplify the Equation
Expanding the equation:
6x+5x−10+4x−20=120
Combining like terms:
15x−30=120
Adding 30 to both sides:
15x=150
Dividing by 15:
x=10
Step 7: Calculate Work Done by Each Person
Now we can calculate how much work each person did:
- A's work: 6×10=60 units.
- B's work: 5×8=40 units (B worked for 8 days).
- C's work: 4×5=20 units (C worked for 5 days).
Step 8: Calculate the Share of A
The total work is 120 units, and the payment is Rs. 5400. The share of A can be calculated as follows:
Share of A=Work done by ATotal work×Total payment
Share of A=60120×5400=12×5400=2700
Final Answer
Thus, the share of A from the assured money is Rs. 2700.
---
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 24 days, so B's work rate is 124 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.
To find a common measure for the work done, we can take the least common multiple (LCM) of the days:
- The LCM of 20, 24, and 30 is 120.
- Therefore, the total work can be assumed to be 120 units.
Now, we calculate the work done by each person in terms of units:
- A's work in 120 units: 12020=6 units per day.
- B's work in 120 units: 12024=5 units per day.
- C's work in 120 units: 12030=4 units per day.
The combined work done by A, B, and C in one day is:
- Total work rate = 6+5+4=15 units per day.
Let’s assume they worked together for x days. Since B left 2 days before the completion and C left 5 days before the completion, we can express the total work done as:
- A worked for x days.
- B worked for x−2 days.
- C worked for x−5 days.
6x+5(x−2)+4(x−5)=120
Expanding the equation:
6x+5x−10+4x−20=120
Combining like terms:
15x−30=120
Adding 30 to both sides:
15x=150
Dividing by 15:
x=10
Now we can calculate how much work each person did:
- A's work: 6×10=60 units.
- B's work: 5×8=40 units (B worked for 8 days).
- C's work: 4×5=20 units (C worked for 5 days).
The total work is 120 units, and the payment is Rs. 5400. The share of A can be calculated as follows:
Share of A=Work done by ATotal work×Total payment
Share of A=60120×5400=12×5400=2700
Thus, the share of A from the assured money is Rs. 2700.
Topper's Solved these Questions
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
Similar Questions
A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24
View SolutionX and Y can do a piece of work in 20 days and 30 days respectively. The time they take to complete the work by working together is ……………
View Solution
Knowledge Check
A, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
A7B10C12D9A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of theseA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these
A, B and C can do work in 20, 25 and 30 days respectively. They undertook to finish the work together for Rs. 2220, then the share of A exceeds that of B by
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View SolutionA, B and C can do a piece of work in 36, 54 and days respectively. They started the work but A left days before the completion of the work while B 12 days before the completion. The number of days for which C worked is 4 b. 8 c. 12 d. 24
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View Solution