A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24
To solve the problem, we need to determine how many days C worked given the work rates of A, B, and C, and the conditions of when they left the work.
1. Determine the work rates of A, B, and C:
- A can complete the work in 36 days, so A's work rate is 136 of the work per day.
- B can complete the work in 54 days, so B's work rate is 154 of the work per day.
- C can complete the work in 72 days, so C's work rate is 172 of the work per day.
2. Calculate the combined work rate of A, B, and C:
Combined work rate=136+154+172
To add these fractions, we need a common denominator. The least common multiple (LCM) of 36, 54, and 72 is 216.
136=6216,154=4216,172=3216
Thus,
Combined work rate=6+4+3216=13216
3. Let the total work be 1 unit. Calculate the total time taken to complete the work:
- Let x be the total number of days to complete the work.
- The work done by A, B, and C together for x−12 days (since B leaves 12 days before completion) is:
(x−12)⋅13216
- After B leaves, A and C work together for x−8 days (since A leaves 8 days before completion):
(x−8)⋅(136+172)=(x−8)⋅1+1236=(x−8)⋅372=(x−8)⋅124
- The total work done is:
(x−12)⋅13216+(x−8)⋅124=1
4. Solve for x:
- Convert 124 to a fraction with a denominator of 216:
124=9216
- The equation becomes:
(x−12)⋅13216+(x−8)⋅9216=1
- Multiply through by 216 to eliminate the denominator:
13(x−12)+9(x−8)=216
- Expand and simplify:
13x−156+9x−72=216
22x−228=216
22x=444
x=20.18 days (approximately)
5. Determine how many days C worked:
- C worked for the total duration x plus the days A and B worked before they left:
- C worked for x days, and since A worked for x−8 days and B for x−12 days:
- C worked for the last 8 days alone, plus the days worked together with A and B.
- Total days C worked:
20.18+8=24 days
Final Answer:
C worked for 24 days.
- A can complete the work in 36 days, so A's work rate is 136 of the work per day.
- B can complete the work in 54 days, so B's work rate is 154 of the work per day.
- C can complete the work in 72 days, so C's work rate is 172 of the work per day.
Combined work rate=136+154+172
To add these fractions, we need a common denominator. The least common multiple (LCM) of 36, 54, and 72 is 216.
136=6216,154=4216,172=3216
Thus,
Combined work rate=6+4+3216=13216
- Let x be the total number of days to complete the work.
- The work done by A, B, and C together for x−12 days (since B leaves 12 days before completion) is:
(x−12)⋅13216
- After B leaves, A and C work together for x−8 days (since A leaves 8 days before completion):
(x−8)⋅(136+172)=(x−8)⋅1+1236=(x−8)⋅372=(x−8)⋅124
- The total work done is:
(x−12)⋅13216+(x−8)⋅124=1
- Convert 124 to a fraction with a denominator of 216:
124=9216
- The equation becomes:
(x−12)⋅13216+(x−8)⋅9216=1
- Multiply through by 216 to eliminate the denominator:
13(x−12)+9(x−8)=216
- Expand and simplify:
13x−156+9x−72=216
22x−228=216
22x=444
x=20.18 days (approximately)
- C worked for the total duration x plus the days A and B worked before they left:
- C worked for x days, and since A worked for x−8 days and B for x−12 days:
- C worked for the last 8 days alone, plus the days worked together with A and B.
- Total days C worked:
20.18+8=24 days
C worked for 24 days.
Topper's Solved these Questions
Similar Questions
A, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA, B and C can do a work in 10, 12 and 15 days respectively. All three start the work together but A left 5 days before the completion of the work and after 2 days B left, how much time shall be taken to do whole work?
View Solution
Knowledge Check
- Question 1 - Select One
A, B and C can do a piece of work in 36, 54 and days respectively. They started the work but A left days before the completion of the work while B 12 days before the completion. The number of days for which C worked is 4 b. 8 c. 12 d. 24
A4B8C12D24 - Question 2 - Select One
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these - Question 3 - Select One
A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these
A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View SolutionA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA B and C can complete a piece of work in 24, 6 and 12 days respectively. They will complete the same work in :
View SolutionA, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
View Solution