Doubtnut Promotions Sticky

A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to determine how many days C worked given the work rates of A, B, and C, and the conditions of when they left the work.

1. Determine the work rates of A, B, and C:
- A can complete the work in 36 days, so A's work rate is 136 of the work per day.
- B can complete the work in 54 days, so B's work rate is 154 of the work per day.
- C can complete the work in 72 days, so C's work rate is 172 of the work per day.

2. Calculate the combined work rate of A, B, and C:
Combined work rate=136+154+172
To add these fractions, we need a common denominator. The least common multiple (LCM) of 36, 54, and 72 is 216.
136=6216,154=4216,172=3216
Thus,
Combined work rate=6+4+3216=13216

3. Let the total work be 1 unit. Calculate the total time taken to complete the work:
- Let x be the total number of days to complete the work.
- The work done by A, B, and C together for x12 days (since B leaves 12 days before completion) is:
(x12)13216
- After B leaves, A and C work together for x8 days (since A leaves 8 days before completion):
(x8)(136+172)=(x8)1+1236=(x8)372=(x8)124
- The total work done is:
(x12)13216+(x8)124=1

4. Solve for x:
- Convert 124 to a fraction with a denominator of 216:
124=9216
- The equation becomes:
(x12)13216+(x8)9216=1
- Multiply through by 216 to eliminate the denominator:
13(x12)+9(x8)=216
- Expand and simplify:
13x156+9x72=216
22x228=216
22x=444
x=20.18 days (approximately)

5. Determine how many days C worked:
- C worked for the total duration x plus the days A and B worked before they left:
- C worked for x days, and since A worked for x8 days and B for x12 days:
- C worked for the last 8 days alone, plus the days worked together with A and B.
- Total days C worked:
20.18+8=24 days

Final Answer:
C worked for 24 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can do a piece of work in 36, 54 and days respectively. They started the work but A left days before the completion of the work while B 12 days before the completion. The number of days for which C worked is 4 b. 8 c. 12 d. 24

    A4
    B8
    C12
    D24
  • Question 2 - Select One

    A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these
  • Question 3 - Select One

    A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these