40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
5623 days
5313 days
52 days
50 days
The correct Answer is:A
Step by step video, text & image solution for 40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Similar Questions
15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 men left the work .View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution
Knowledge Check
- Question 1 - Select One
40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
AA. 5623 daysBB. 5313 daysCC. 52 daysDD. 50 days - Question 2 - Select One
60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
A36B30C40D45 - Question 3 - Select One
50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
A60B30C40D50
50 people can complete a work in 50 days. They started the work together but at the end of every 10th day 5 people join the work. In how much time the work would be completed?
View Solution40 people can complete a work in 40 days. They started the work together but 5 people had to leave the work on every tenth day. In how much time the work would be completed?
View Solution25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
View Solution15 men can complete a work in 210 days. They started the work but at the end of 10 days, 15 additional men, with double efficiency, were in- ducted. How many days in all did they take to finish the work ?
View Solution3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C start work together but A left the work after two days. and B left the work 1 day before the completion of the work. In how much time the whole work will be completed?
View Solution