25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
36 days
88 days
94 days
None of these
The correct Answer is:A
To solve the problem step by step, let's break it down:
Step 1: Calculate the total work done by 25 men and 15 women in 12 days.
- Let the work done by 1 man in 1 day be M and the work done by 1 woman in 1 day be W.
- The total work done by 25 men and 15 women in 12 days can be expressed as:
(25M+15W)×12=Total Work
Step 2: Calculate the total work done in terms of efficiency.
- We can simplify the equation:
25M+15W=Total Work12
Step 3: Work done in 8 days by 25 men and 15 women.
- In 8 days, the work done is:
(25M+15W)×8
Step 4: Calculate the remaining work after 8 days.
- The remaining work after 8 days is:
Remaining Work=Total Work−(25M+15W)×8
Step 5: Work done by 25 men in the next 6 days.
- The remaining work is completed by 25 men in 6 days:
25M×6=Remaining Work
Step 6: Set up the equation for total work.
- From the above steps, we can equate the remaining work:
(25M+15W)×12−(25M+15W)×8=25M×6
- Simplifying gives:
(25M+15W)×4=25M×6
Step 7: Solve for the ratio of men's and women's work.
- Rearranging gives:
25M+15W=25M×64
- This simplifies to:
25M+15W=37.5M
- Therefore:
15W=12.5M⟹MW=1512.5=65
Step 8: Calculate the total work in terms of women’s work.
- Let’s denote the total work as T:
T=25M×12+15W×12
- Substitute M=56W:
T=25(56W)×12+15W×12
T=1256W×12+15W×12
T=250W+180W=430W
Step 9: Calculate the time taken by 15 women to complete the work.
- The work done by 15 women in 1 day is:
15W
- Therefore, the time taken by 15 women to complete the total work T is:
Time=T15W=430W15W=43015=28.67 days
Conclusion
- The time required for 15 women to complete the work is approximately 28.67 days.
- Let the work done by 1 man in 1 day be M and the work done by 1 woman in 1 day be W.
- The total work done by 25 men and 15 women in 12 days can be expressed as:
(25M+15W)×12=Total Work
- We can simplify the equation:
25M+15W=Total Work12
- In 8 days, the work done is:
(25M+15W)×8
- The remaining work after 8 days is:
Remaining Work=Total Work−(25M+15W)×8
- The remaining work is completed by 25 men in 6 days:
25M×6=Remaining Work
- From the above steps, we can equate the remaining work:
(25M+15W)×12−(25M+15W)×8=25M×6
- Simplifying gives:
(25M+15W)×4=25M×6
- Rearranging gives:
25M+15W=25M×64
- This simplifies to:
25M+15W=37.5M
- Therefore:
15W=12.5M⟹MW=1512.5=65
- Let’s denote the total work as T:
T=25M×12+15W×12
- Substitute M=56W:
T=25(56W)×12+15W×12
T=1256W×12+15W×12
T=250W+180W=430W
- The work done by 15 women in 1 day is:
15W
- Therefore, the time taken by 15 women to complete the total work T is:
Time=T15W=430W15W=43015=28.67 days
- The time required for 15 women to complete the work is approximately 28.67 days.
Topper's Solved these Questions
Similar Questions
15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 men left the work .View Solution15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 more men join the work.View Solution
Knowledge Check
- Question 1 - Select One
25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?
A48 daysB24 daysC36 daysD60 days - Question 2 - Select One
25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?
A60 daysB88 daysC94 daysDNone of these - Question 3 - Select One
If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
A21B20C24D22
12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start’ working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to Complete the remaining work, if it is to be completed in 3 days?
View SolutionIf 3 men and 7 women can complete a work in 10 days and 4 men and 6 women need 8 days to complete the same work. In how many days will 10 women complete the same work?
View Solution12 men and 15 women can complete a work in 10 days. In how many days the same work will be completed by 7 men and 10 women?
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View Solution4 men and 6 women complete a work in 8 days. 2 men and 9 women also complete in 8 days in which. The number of days In which 18 women complete the work is :
View Solution