Doubtnut Promotions Sticky

25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?

A

36 days

B

88 days

C

94 days

D

None of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, let's break it down:

Step 1: Calculate the total work done by 25 men and 15 women in 12 days.
- Let the work done by 1 man in 1 day be M and the work done by 1 woman in 1 day be W.
- The total work done by 25 men and 15 women in 12 days can be expressed as:
(25M+15W)×12=Total Work

Step 2: Calculate the total work done in terms of efficiency.
- We can simplify the equation:
25M+15W=Total Work12

Step 3: Work done in 8 days by 25 men and 15 women.
- In 8 days, the work done is:
(25M+15W)×8

Step 4: Calculate the remaining work after 8 days.
- The remaining work after 8 days is:
Remaining Work=Total Work(25M+15W)×8

Step 5: Work done by 25 men in the next 6 days.
- The remaining work is completed by 25 men in 6 days:
25M×6=Remaining Work

Step 6: Set up the equation for total work.
- From the above steps, we can equate the remaining work:
(25M+15W)×12(25M+15W)×8=25M×6
- Simplifying gives:
(25M+15W)×4=25M×6

Step 7: Solve for the ratio of men's and women's work.
- Rearranging gives:
25M+15W=25M×64
- This simplifies to:
25M+15W=37.5M
- Therefore:
15W=12.5MMW=1512.5=65

Step 8: Calculate the total work in terms of women’s work.
- Let’s denote the total work as T:
T=25M×12+15W×12
- Substitute M=56W:
T=25(56W)×12+15W×12
T=1256W×12+15W×12
T=250W+180W=430W

Step 9: Calculate the time taken by 15 women to complete the work.
- The work done by 15 women in 1 day is:
15W
- Therefore, the time taken by 15 women to complete the total work T is:
Time=T15W=430W15W=43015=28.67 days

Conclusion
- The time required for 15 women to complete the work is approximately 28.67 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?

    A48 days
    B24 days
    C36 days
    D60 days
  • Question 2 - Select One

    25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?

    A60 days
    B88 days
    C94 days
    DNone of these
  • Question 3 - Select One

    If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?

    A21
    B20
    C24
    D22