15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 men left the work .
The correct Answer is:16 days
To solve the problem step by step, we will first determine the total amount of work and then calculate how the work progresses over the days with the changes in the number of workers.
Step 1: Calculate the Total Work
Given that 15 men can complete the work in 12 days, we can calculate the total work in terms of "man-days".
Total work = Number of men × Number of days
Total work = 15 men × 12 days = 180 man-days
Step 2: Work Done in the First 4 Days
Next, we need to find out how much work is completed in the first 4 days by the 15 men.
Work done in 4 days = Number of men × Number of days
Work done in 4 days = 15 men × 4 days = 60 man-days
Step 3: Calculate Remaining Work
Now, we can find the remaining work after the first 4 days.
Remaining work = Total work - Work done in 4 days
Remaining work = 180 man-days - 60 man-days = 120 man-days
Step 4: Determine the New Number of Workers
After 4 days, 5 men leave the work, so the number of men left is:
Number of men left = 15 men - 5 men = 10 men
Step 5: Calculate Days Required to Finish Remaining Work
Now we need to find out how many days it will take for the remaining 10 men to finish the remaining work of 120 man-days.
Days required = Remaining work / Number of men
Days required = 120 man-days / 10 men = 12 days
Step 6: Calculate Total Days to Complete the Work
Finally, we add the 4 days worked initially to the 12 days required to finish the remaining work.
Total days = Days worked initially + Days required to finish remaining work
Total days = 4 days + 12 days = 16 days
Conclusion
The total work will be finished in 16 days.
---
Given that 15 men can complete the work in 12 days, we can calculate the total work in terms of "man-days".
Total work = 15 men × 12 days = 180 man-days
Next, we need to find out how much work is completed in the first 4 days by the 15 men.
Work done in 4 days = 15 men × 4 days = 60 man-days
Now, we can find the remaining work after the first 4 days.
Remaining work = 180 man-days - 60 man-days = 120 man-days
After 4 days, 5 men leave the work, so the number of men left is:
Now we need to find out how many days it will take for the remaining 10 men to finish the remaining work of 120 man-days.
Days required = 120 man-days / 10 men = 12 days
Finally, we add the 4 days worked initially to the 12 days required to finish the remaining work.
Total days = 4 days + 12 days = 16 days
The total work will be finished in 16 days.
Topper's Solved these Questions
Similar Questions
15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 more men join the work.
View SolutionA can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View Solution
Knowledge Check
14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
A9 daysB5 daysC6 daysD7 daysTwelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
A2B4C5D612 men and 15 women can complete a work in 10 days. In how many days the same work will be completed by 7 men and 10 women?
A12B10C9D8
7 men can complete a work in 12 day. They started the work and after 5 days, two men left. In how many days will the work be completed by the remaining men? a.5 b.6 c.7 d.8 e. none of these
View SolutionIf 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View Solution60 men can complete a work in 30 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
View Solution50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?
View Solution