15 men can complete a work in 12 days they start the work together . In how many days the total work will be finished when.
After 4 days 5 men left the work .

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:16 days


To solve the problem step by step, we will first determine the total amount of work and then calculate how the work progresses over the days with the changes in the number of workers.

Step 1: Calculate the Total Work
Given that 15 men can complete the work in 12 days, we can calculate the total work in terms of "man-days".

Total work = Number of men × Number of days
Total work = 15 men × 12 days = 180 man-days

Step 2: Work Done in the First 4 Days
Next, we need to find out how much work is completed in the first 4 days by the 15 men.

Work done in 4 days = Number of men × Number of days
Work done in 4 days = 15 men × 4 days = 60 man-days

Step 3: Calculate Remaining Work
Now, we can find the remaining work after the first 4 days.

Remaining work = Total work - Work done in 4 days
Remaining work = 180 man-days - 60 man-days = 120 man-days

Step 4: Determine the New Number of Workers
After 4 days, 5 men leave the work, so the number of men left is:

Number of men left = 15 men - 5 men = 10 men

Step 5: Calculate Days Required to Finish Remaining Work
Now we need to find out how many days it will take for the remaining 10 men to finish the remaining work of 120 man-days.

Days required = Remaining work / Number of men
Days required = 120 man-days / 10 men = 12 days

Step 6: Calculate Total Days to Complete the Work
Finally, we add the 4 days worked initially to the 12 days required to finish the remaining work.

Total days = Days worked initially + Days required to finish remaining work
Total days = 4 days + 12 days = 16 days

Conclusion
The total work will be finished in 16 days.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?

    A9 days
    B5 days
    C6 days
    D7 days
  • Twelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?

    A2
    B4
    C5
    D6
  • 12 men and 15 women can complete a work in 10 days. In how many days the same work will be completed by 7 men and 10 women?

    A12
    B10
    C9
    D8