Doubtnut Promotions Sticky

'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is

A

6

B

10

C

12

D

15

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's define the variables and set up the equations based on the information provided.

Step 1: Define the variables
Let x be the original number of men. According to the problem, these x men can complete the work in 30 days.

Step 2: Calculate the total work
The total work can be expressed in terms of man-days. Since x men complete the work in 30 days, the total work W is:
W=x×30

Step 3: Set up the equation for the new scenario
If there are 6 more men, the total number of men becomes x+6. The work can now be completed in 20 days (30 days - 10 days). Therefore, the total work can also be expressed as:
W=(x+6)×20

Step 4: Set the two expressions for work equal to each other
Since both expressions represent the same total work W, we can set them equal:
x×30=(x+6)×20

Step 5: Expand and simplify the equation
Expanding the right side:
30x=20x+120

Step 6: Rearranging the equation
Now, we can rearrange the equation to isolate x:
30x20x=120
10x=120

Step 7: Solve for x
Dividing both sides by 10 gives:
x=12

Conclusion
The original number of men is 12.

---

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:

    A36
    B40
    C30
    D32
  • Question 2 - Select One

    A certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :

    A6
    B12
    C18
    D24
  • Question 3 - Select One

    A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:

    A30
    B40
    C32
    D36