A certain number of men can do a piece of work in 40 days. If there were 45 men more the work could have been finished in 25 days. Find the original number of men employed in the work (A) 70 (B) 85 (C) 65 (D) 75
A
B
C
D
To solve the problem step by step, we will use the information provided in the question to set up equations and find the original number of men employed in the work.
Step 1: Define the variables
Let x be the original number of men employed to do the work.
Step 2: Calculate the total work done
The total work can be expressed in terms of men and days. If x men can complete the work in 40 days, the total amount of work (in man-days) is:
Total Work=x×40
Step 3: Set up the equation with the increased number of men
If 45 more men are employed, the total number of men becomes x+45. With this increased workforce, the work can be completed in 25 days. Thus, the total work can also be expressed as:
Total Work=(x+45)×25
Step 4: Set the two expressions for total work equal to each other
Since both expressions represent the same total work, we can set them equal:
x×40=(x+45)×25
Step 5: Expand and simplify the equation
Expanding the right side gives:
40x=25x+1125
Step 6: Rearrange the equation to isolate x
Subtract 25x from both sides:
40x−25x=1125
15x=1125
Step 7: Solve for x
Now, divide both sides by 15:
x=112515
x=75
Conclusion
The original number of men employed in the work is 75.
Final Answer
The correct option is (D) 75.
---
Let x be the original number of men employed to do the work.
The total work can be expressed in terms of men and days. If x men can complete the work in 40 days, the total amount of work (in man-days) is:
Total Work=x×40
If 45 more men are employed, the total number of men becomes x+45. With this increased workforce, the work can be completed in 25 days. Thus, the total work can also be expressed as:
Total Work=(x+45)×25
Since both expressions represent the same total work, we can set them equal:
x×40=(x+45)×25
Expanding the right side gives:
40x=25x+1125
Subtract 25x from both sides:
40x−25x=1125
15x=1125
Now, divide both sides by 15:
x=112515
x=75
The original number of men employed in the work is 75.
The correct option is (D) 75.
Similar Questions
A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View SolutionA certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
View Solution
Knowledge Check
- Question 1 - Select One
'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
A6B10C12D15 - Question 2 - Select One
'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
A6B10C12D15 - Question 3 - Select One
A certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :
A6B12C18D24
A certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
View SolutionA certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?
View SolutionA certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?
View SolutionA certain number of men can do a work in 40 days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially ?
View SolutionA certain number of men can do a work in 60 days. If there were 8 men less it could be finished in 10 days more. How many men are there?
View Solution