Doubtnut Promotions Sticky

A certain number of men can do a piece of work in 40 days. If there were 45 men more the work could have been finished in 25 days. Find the original number of men employed in the work (A) 70 (B) 85 (C) 65 (D) 75

A

A

B

B

C

C

D

D

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will use the information provided in the question to set up equations and find the original number of men employed in the work.

Step 1: Define the variables
Let x be the original number of men employed to do the work.

Step 2: Calculate the total work done
The total work can be expressed in terms of men and days. If x men can complete the work in 40 days, the total amount of work (in man-days) is:
Total Work=x×40

Step 3: Set up the equation with the increased number of men
If 45 more men are employed, the total number of men becomes x+45. With this increased workforce, the work can be completed in 25 days. Thus, the total work can also be expressed as:
Total Work=(x+45)×25

Step 4: Set the two expressions for total work equal to each other
Since both expressions represent the same total work, we can set them equal:
x×40=(x+45)×25

Step 5: Expand and simplify the equation
Expanding the right side gives:
40x=25x+1125

Step 6: Rearrange the equation to isolate x
Subtract 25x from both sides:
40x25x=1125
15x=1125

Step 7: Solve for x
Now, divide both sides by 15:
x=112515
x=75

Conclusion
The original number of men employed in the work is 75.

Final Answer
The correct option is (D) 75.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is

    A6
    B10
    C12
    D15
  • Question 2 - Select One

    'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is

    A6
    B10
    C12
    D15
  • Question 3 - Select One

    A certain number of men can do a plece of work in 60 days. If there were 6 men more, the work can be finished 20 days earlier. The number of men working is :

    A6
    B12
    C18
    D24