P can do a job in 12 days and Q can do the same job in 6 days, in how many days working together they can complete the job?
To solve the problem of how many days P and Q can complete the job together, we can follow these steps:
1. Determine the Work Done by Each Person:
- Let the total work be represented as 12 units (the LCM of 12 and 6, which are the days taken by P and Q respectively).
- P can complete the job in 12 days, so in 1 day, P does:
Work done by P in 1 day=12 units12 days=1 unit/day
- Q can complete the job in 6 days, so in 1 day, Q does:
Work done by Q in 1 day=12 units6 days=2 units/day
2. Calculate the Combined Efficiency:
- When P and Q work together, their combined efficiency is:
Combined efficiency=Efficiency of P+Efficiency of Q=1 unit/day+2 units/day=3 units/day
3. Calculate the Total Time Taken to Complete the Work:
- The total time taken by both P and Q to complete the job together can be calculated using the formula:
Total time=Total workCombined efficiency=12 units3 units/day=4 days
Final Answer:
P and Q, working together, can complete the job in 4 days.
---
- Let the total work be represented as 12 units (the LCM of 12 and 6, which are the days taken by P and Q respectively).
- P can complete the job in 12 days, so in 1 day, P does:
Work done by P in 1 day=12 units12 days=1 unit/day
- Q can complete the job in 6 days, so in 1 day, Q does:
Work done by Q in 1 day=12 units6 days=2 units/day
- When P and Q work together, their combined efficiency is:
Combined efficiency=Efficiency of P+Efficiency of Q=1 unit/day+2 units/day=3 units/day
- The total time taken by both P and Q to complete the job together can be calculated using the formula:
Total time=Total workCombined efficiency=12 units3 units/day=4 days
P and Q, working together, can complete the job in 4 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone
A60B30C45D40 - Question 2 - Select One
A company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?
A4/3 daysB3 daysC3 daysD12 days - Question 3 - Select One
22 men can complete a job in 16days. In how many days, will 32 men complete that job?
A14B12C16D11
A and B working together can do a piece of work in 12 days, B and C can do it in 15 days nd C and A can do the same work in 20 days b. How long would each of them take to complete the job?
View SolutionIf A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?
View SolutionA, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?
View SolutionRohan and Rohit together can do a certain job in 10 days while Rohan alone can do the same job in 15 days. How many days Rohit alone will do the same job ?
View Solution