Doubtnut Promotions Sticky

8 men and 4 woment together can complete a piece ot work in 6 days. Work done by a man in one day is double the work done by a women in one day 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined the work.
Quantity I: more days required to complete the work
II: 5 days

A

Quantity I= Quantity II or No relation

B

Quantity I Quantity II

C

Quantity I< Quantity II

D

Quantity I le Quantity II

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we need to analyze the work done by men and women, and how the workforce changes over time.

Step 1: Calculate the total work done by 8 men and 4 women in 6 days.

Given that:
- 8 men and 4 women can complete the work in 6 days.
- The work done by a man in one day is double that of a woman.

Let the work done by one woman in one day be W. Then, the work done by one man in one day is 2W.

Thus, the total work done by 8 men and 4 women in one day is:
Total work in one day=8×2W+4×W=16W+4W=20W

In 6 days, the total work done is:
Total work=20W×6=120W

Step 2: Calculate the work done in the first 2 days.

In 2 days, the total work done by 8 men and 4 women is:
Work done in 2 days=20W×2=40W

Step 3: Calculate the remaining work.

The remaining work after 2 days is:
Remaining work=120W40W=80W

Step 4: Analyze the change in workforce.

After 2 days, 4 men leave, and 4 new women join.

- The remaining workforce consists of:
- 4 men (since 8 - 4 = 4)
- 8 women (since 4 + 4 = 8)

The total work done by the new workforce in one day is:
Work done by 4 men and 8 women=4×2W+8×W=8W+8W=16W

Step 5: Calculate the number of days required to complete the remaining work.

To find out how many days are required to complete the remaining work of 80W with the new workforce:
Days required=Remaining workWork done per day=80W16W=5 days

Step 6: Compare the quantities.

- Quantity I: More days required to complete the work = 5 days
- Quantity II: 5 days

Conclusion:

Both quantities are equal. Therefore, the answer is that Quantity I is equal to Quantity II.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?

    A5 days
    B8 days
    C6 days
    D4 days
  • Question 2 - Select One

    8 men and 4 women together can complete a piece of work in
    6 days. The work done by a man in one day is diuble the
    work done by a woman in one day. If 8 men and 4 women
    started working and after 2 days 4 men left and 4 new women
    joined, in how many more days will the work be complete?

    A5 days
    B8 days
    C6 days
    D4 days
  • Question 3 - Select One

    8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed

    A7 days
    B6 days
    C5.25 days
    D3.7 days