8 men and 4 woment together can complete a piece ot work in 6 days. Work done by a man in one day is double the work done by a women in one day 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined the work.
Quantity I: more days required to complete the work
II: 5 days
Quantity I= Quantity II or No relation
Quantity I≥ Quantity II
Quantity I< Quantity II
Quantity I le Quantity II
The correct Answer is:A
To solve the problem step by step, we need to analyze the work done by men and women, and how the workforce changes over time.
Step 1: Calculate the total work done by 8 men and 4 women in 6 days.
Given that:
- 8 men and 4 women can complete the work in 6 days.
- The work done by a man in one day is double that of a woman.
Let the work done by one woman in one day be W. Then, the work done by one man in one day is 2W.
Thus, the total work done by 8 men and 4 women in one day is:
Total work in one day=8×2W+4×W=16W+4W=20W
In 6 days, the total work done is:
Total work=20W×6=120W
Step 2: Calculate the work done in the first 2 days.
In 2 days, the total work done by 8 men and 4 women is:
Work done in 2 days=20W×2=40W
Step 3: Calculate the remaining work.
The remaining work after 2 days is:
Remaining work=120W−40W=80W
Step 4: Analyze the change in workforce.
After 2 days, 4 men leave, and 4 new women join.
- The remaining workforce consists of:
- 4 men (since 8 - 4 = 4)
- 8 women (since 4 + 4 = 8)
The total work done by the new workforce in one day is:
Work done by 4 men and 8 women=4×2W+8×W=8W+8W=16W
Step 5: Calculate the number of days required to complete the remaining work.
To find out how many days are required to complete the remaining work of 80W with the new workforce:
Days required=Remaining workWork done per day=80W16W=5 days
Step 6: Compare the quantities.
- Quantity I: More days required to complete the work = 5 days
- Quantity II: 5 days
Conclusion:
Both quantities are equal. Therefore, the answer is that Quantity I is equal to Quantity II.
---
- 8 men and 4 women can complete the work in 6 days.
- The work done by a man in one day is double that of a woman.
Total work in one day=8×2W+4×W=16W+4W=20W
Total work=20W×6=120W
Work done in 2 days=20W×2=40W
Remaining work=120W−40W=80W
- 4 men (since 8 - 4 = 4)
- 8 women (since 4 + 4 = 8)
Work done by 4 men and 8 women=4×2W+8×W=8W+8W=16W
Days required=Remaining workWork done per day=80W16W=5 days
- Quantity II: 5 days
Topper's Solved these Questions
Similar Questions
Three men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?
View Solution10 men and 8 women can together complete a work in 5 days. Work done by a woman is equal to the half of the work done by a man. In how many days, will 4 men and 6 women complete that work ?
View Solution
Knowledge Check
- Question 1 - Select One
8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed?
A5 daysB8 daysC6 daysD4 days - Question 2 - Select One
8 men and 4 women together can complete a piece of work in
6 days. The work done by a man in one day is diuble the
work done by a woman in one day. If 8 men and 4 women
started working and after 2 days 4 men left and 4 new women
joined, in how many more days will the work be complete?A5 daysB8 daysC6 daysD4 days - Question 3 - Select One
8 men and 5 women together can complete a piece of work in 7 days and work done by a women in one day is half the work done by a man in one day. If 9 men and 3 women started working and after 4 days 4 men left the work and 4 new women joined then, in how many many more days will the work be completed
A7 daysB6 daysC5.25 daysD3.7 days
10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?
View Solution2 men and 3 women together or 4 men together can complete a piece of work in 20 days.3 men and 3 women will complete the same work in :
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View SolutionWhen 6 men and 8 women can do a piece of work in 15 days, then 11 men and 16 women can do the same work in 8 days. In how many days can 4 men and 4 women do the work ?
View Solution