Doubtnut Promotions Sticky

A can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last?

A

4.5days

B

6days

C

9.5days

D

12days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Determine the work done by A, B, and C in one day.
- A can complete the work in 16 days, so A's work in one day = 116 of the work.
- B can complete the work in 12 days, so B's work in one day = 112 of the work.
- C can complete the work in 15 days, so C's work in one day = 115 of the work.

Step 2: Find the LCM of the denominators to calculate the total work.
- The LCM of 16, 12, and 15 is 240.
- Therefore, the total work can be considered as 240 units.

Step 3: Calculate the daily work of A, B, and C in units.
- A's work in one day = 24016=15 units.
- B's work in one day = 24012=20 units.
- C's work in one day = 24015=16 units.

Step 4: Calculate the total work done by A, B, and C in the first 2 days.
- In 2 days, A, B, and C together will do:
Total work in 2 days=2×(A+B+C)=2×(15+20+16)=2×51=102 units

Step 5: Calculate the remaining work after A leaves.
- Total work = 240 units.
- Work done in the first 2 days = 102 units.
- Remaining work = 240102=138 units.

Step 6: Determine when B leaves the work.
- Let the total time taken to complete the work be x days.
- B leaves 3 days before the work is completed, so B works for x3 days.

Step 7: Calculate the work done by B and C after A leaves.
- From day 3 to x3, B and C work together.
- Work done by B in x3 days = 20×(x3) units.
- Work done by C in x days = 16×(x3) units.

Step 8: Calculate the total work done by B and C.
- Total work done by B and C from day 3 to x:
Total work by B and C=20(x3)+16(x3)=36(x3)

Step 9: Set up the equation for total work.
- The total work done by A, B, and C must equal 240 units:
102+36(x3)+16×3=240
102+36(x3)+48=240
36(x3)+150=240
36(x3)=90
x3=9036=2.5
x=5.5

Step 10: Calculate the total time worked.
- Since A worked for 2 days, and B worked for 5.53=2.5 days, the total duration of the work is:
Total time=2+2.5+3=7.5 days

Final Answer:
The total duration of the work lasted 7.5 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C start work together but A left the work after two days. and B left the work 1 day before the completion of the work. In how much time the whole work will be completed?

    A589
    B289
    C6
    D5
  • Question 2 - Select One

    A, B and C can complete a work in 8, 16 and 24 days respectively. They start the work together and A works till last moment . If C leaves the work 2 days before and B leaves one day before the completion of the work, in how many days the work will be finished?

    A8 days
    B5 days
    C6 days
    D7 days
  • Question 3 - Select One

    A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?

    A10
    B12
    C15
    D16