Doubtnut Promotions Sticky

A can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last?

A

4.5days

B

6days

C

9.5days

D

12days

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    3 men A, B and C can complete the work in 10, 12 and 15 days. A, B, C start work together but A left the work after two days. and B left the work 1 day before the completion of the work. In how much time the whole work will be completed?

    A589
    B289
    C6
    D5
  • Question 1 - Select One

    A, B and C can complete a work in 8, 16 and 24 days respectively. They start the work together and A works till last moment . If C leaves the work 2 days before and B leaves one day before the completion of the work, in how many days the work will be finished?

    A8 days
    B5 days
    C6 days
    D7 days
  • Question 1 - Select One

    A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?

    A10
    B12
    C15
    D16
  • Question 1 - Select One

    Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?

    A5 days
    B6 days
    C7 days
    D8 days
  • Question 1 - Select One

    A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

    A10 days
    B12 days
    C15 days
    D16 days
  • Question 1 - Select One

    A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be

    A6 days
    B8 days
    C9 days
    D5 days
  • Question 1 - Select One

    A can complete a piece of work In 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

    A10 days
    B12 days
    C15 days
    D16 days
  • Question 1 - Select One

    P can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?

    A8
    B10
    C9
    D11

Similar Questions