Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?
5 days
6 days
7 days
8 days
The correct Answer is:C
To solve the problem step by step, we will first determine the work done by each person, then calculate the total work, and finally find out how many days it takes to complete the work under the given conditions.
Step 1: Determine the work rate of each person
- Raju can complete the work in 10 days, so his work rate is:
Raju's rate=110 work/day=6 units/day
- Vicky can complete the work in 12 days, so his work rate is:
Vicky's rate=112 work/day=5 units/day
- Tinku can complete the work in 15 days, so his work rate is:
Tinku's rate=115 work/day=4 units/day
Step 2: Calculate the total work
The total work can be calculated using the least common multiple (LCM) of their days to complete the work:
- LCM of 10, 12, and 15 is 60 units. Therefore, the total work is 60 units.
Step 3: Calculate the work done in the first 2 days
When Raju, Vicky, and Tinku work together for the first 2 days:
- Combined work rate for all three:
Total rate=6+5+4=15 units/day
- Work done in 2 days:
Work done=15 units/day×2 days=30 units
Step 4: Calculate remaining work
After 2 days, the remaining work is:
Remaining work=60 units−30 units=30 units
Step 5: Determine when Vicky leaves
Let x be the total number of days taken to complete the work. Vicky leaves 3 days before the work is completed, so he works for x−3 days.
Step 6: Calculate the work done by Vicky and Tinku after Raju leaves
After Raju leaves, only Vicky and Tinku are working. Their combined work rate is:
Vicky's rate+Tinku's rate=5+4=9 units/day
Let y be the number of days Vicky and Tinku work together after Raju leaves. Since Raju worked for 2 days, the total time they work together is:
y=x−2
Step 7: Set up the equation for remaining work
The work done by Vicky and Tinku in y days is:
9y=30 units
Substituting y=x−2:
9(x−2)=30
Step 8: Solve for x
Expanding the equation:
9x−18=30
Adding 18 to both sides:
9x=48
Dividing by 9:
x=489=163≈5.33 days
Step 9: Calculate total days of work
Since Vicky leaves 3 days before the work is completed, we can find the total days:
x=5.33+3=8.33 days
Final Calculation
Since the work is completed in whole days, we round up to the nearest whole number:
Total days to complete the work=7 days
Conclusion
The work is completed in 7 days.
- Raju can complete the work in 10 days, so his work rate is:
Raju's rate=110 work/day=6 units/day
- Vicky can complete the work in 12 days, so his work rate is:
Vicky's rate=112 work/day=5 units/day
- Tinku can complete the work in 15 days, so his work rate is:
Tinku's rate=115 work/day=4 units/day
The total work can be calculated using the least common multiple (LCM) of their days to complete the work:
- LCM of 10, 12, and 15 is 60 units. Therefore, the total work is 60 units.
When Raju, Vicky, and Tinku work together for the first 2 days:
- Combined work rate for all three:
Total rate=6+5+4=15 units/day
- Work done in 2 days:
Work done=15 units/day×2 days=30 units
After 2 days, the remaining work is:
Remaining work=60 units−30 units=30 units
Let x be the total number of days taken to complete the work. Vicky leaves 3 days before the work is completed, so he works for x−3 days.
After Raju leaves, only Vicky and Tinku are working. Their combined work rate is:
Vicky's rate+Tinku's rate=5+4=9 units/day
Let y be the number of days Vicky and Tinku work together after Raju leaves. Since Raju worked for 2 days, the total time they work together is:
y=x−2
The work done by Vicky and Tinku in y days is:
9y=30 units
Substituting y=x−2:
9(x−2)=30
Expanding the equation:
9x−18=30
Adding 18 to both sides:
9x=48
Dividing by 9:
x=489=163≈5.33 days
Since Vicky leaves 3 days before the work is completed, we can find the total days:
x=5.33+3=8.33 days
Since the work is completed in whole days, we round up to the nearest whole number:
Total days to complete the work=7 days
The work is completed in 7 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)
37 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)
27 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself
15 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
A can do a piece of work in 10 days , B in 12 days and C in 15 days.All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished.How long did the work last?
View SolutionA can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last?
View Solution
Knowledge Check
P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?
A10B11C10711D10911P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?
A10B11C10711D10911P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?
A10B11C10711D10911
A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View SolutionA can complete a work in 24 days, B in 32 days and C in 64 days. They start together. A works for 6 days and leaves and B leaves 6 days before the work is finished. In how many days was the work finished?
View SolutionA can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?
View SolutionP can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? 4 b. 15 c. 7 d. 8
View Solution