Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?

A

5 days

B

6 days

C

7 days

D

8 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work done by each person, then calculate the total work, and finally find out how many days it takes to complete the work under the given conditions.

Step 1: Determine the work rate of each person
- Raju can complete the work in 10 days, so his work rate is:
Raju's rate=110 work/day=6 units/day
- Vicky can complete the work in 12 days, so his work rate is:
Vicky's rate=112 work/day=5 units/day
- Tinku can complete the work in 15 days, so his work rate is:
Tinku's rate=115 work/day=4 units/day

Step 2: Calculate the total work
The total work can be calculated using the least common multiple (LCM) of their days to complete the work:
- LCM of 10, 12, and 15 is 60 units. Therefore, the total work is 60 units.

Step 3: Calculate the work done in the first 2 days
When Raju, Vicky, and Tinku work together for the first 2 days:
- Combined work rate for all three:
Total rate=6+5+4=15 units/day
- Work done in 2 days:
Work done=15 units/day×2 days=30 units

Step 4: Calculate remaining work
After 2 days, the remaining work is:
Remaining work=60 units30 units=30 units

Step 5: Determine when Vicky leaves
Let x be the total number of days taken to complete the work. Vicky leaves 3 days before the work is completed, so he works for x3 days.

Step 6: Calculate the work done by Vicky and Tinku after Raju leaves
After Raju leaves, only Vicky and Tinku are working. Their combined work rate is:
Vicky's rate+Tinku's rate=5+4=9 units/day
Let y be the number of days Vicky and Tinku work together after Raju leaves. Since Raju worked for 2 days, the total time they work together is:
y=x2

Step 7: Set up the equation for remaining work
The work done by Vicky and Tinku in y days is:
9y=30 units
Substituting y=x2:
9(x2)=30

Step 8: Solve for x
Expanding the equation:
9x18=30
Adding 18 to both sides:
9x=48
Dividing by 9:
x=489=1635.33 days

Step 9: Calculate total days of work
Since Vicky leaves 3 days before the work is completed, we can find the total days:
x=5.33+3=8.33 days

Final Calculation
Since the work is completed in whole days, we round up to the nearest whole number:
Total days to complete the work=7 days

Conclusion
The work is completed in 7 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

    A10
    B11
    C10711
    D10911
  • P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

    A10
    B11
    C10711
    D10911
  • P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

    A10
    B11
    C10711
    D10911