Doubtnut Promotions Sticky

Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and Jalan together take 10. days to finish the Work What is the difference between number of day taken by Ahluwalia and Jalan when :they worked, alone to complete the whole work?

A

12 days

B

16 days

C

15 days

D

can’t be determined

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to determine the individual work rates of Ahluwalia, Bimal, and Jalan. Let's denote:

- A = number of days taken by Ahluwalia to complete the work alone.
- B = number of days taken by Bimal to complete the work alone.
- J = number of days taken by Jalan to complete the work alone.

Step 1: Establish the equations based on the given information.

1. Ahluwalia and Bimal together take 6 days to finish the work.
This means their combined work rate is:
1A+1B=16

2. Bimal and Jalan together take 10 days to finish the work.
This means their combined work rate is:
1B+1J=110

Step 2: Rearranging the equations.

From the first equation, we can express it as:
1A=161B(1)

From the second equation, we can express it as:
1J=1101B(2)

Step 3: Solve for B in terms of A and J.

From equation (1):
1B=161A

From equation (2):
1B=1101J

Step 4: Set the two expressions for 1B equal to each other.

161A=1101J

Step 5: Cross-multiply to eliminate the fractions.

Cross-multiplying gives us:
(16110)=(1A1J)

Calculating 16110:
5330=230=115

So we have:
1A1J=115

Step 6: Rearranging gives us the difference in days.

This can be expressed as:
1A=1J+115

Taking the reciprocal gives:
A=15JJ+15

Step 7: Find the difference between A and J.

To find the difference |AJ|:
|AJ|=15JJ+15J
=15JJ(J+15)J+15
=15JJ215JJ+15
=J2J+15

Conclusion

The difference between the number of days taken by Ahluwalia and Jalan to complete the work alone cannot be determined without additional information about their individual efficiencies.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together finish a work in 4 day while Aalone finishes the work girl 12 day In how many days will B finish the san work ?

    A5
    B6
    C7
    D8
  • Question 2 - Select One

    A can finish a work in 7 days. B can finish the same work in 9 days. The days required to finish the work by both of them together.

    A11516
    B21516
    C31516
    D41516
  • Question 3 - Select One

    A can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?

    A4.33
    B4.5
    C4.66
    DNone