Doubtnut Promotions Sticky

C is twice efficient as A. B takes thrice as many days as C. A takes 12 days to finish the work alone. If they work in pairs (ie, AB, BC, CA) starting with AB on the first day then BC on the second day and AC on the third day and so on, then how many days are required to finish the work?

A

615 days

B

4.5 days

C

519 days

D

8 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break down the information given and calculate the required work completion time.

Step 1: Determine the efficiencies of A, B, and C

1. Efficiency of A: A takes 12 days to complete the work alone. Therefore, A's efficiency is:
Efficiency of A=1 work12 days=112 work/day

2. Efficiency of C: C is twice as efficient as A. Therefore, C's efficiency is:
Efficiency of C=2×Efficiency of A=2×112=16 work/day

3. Efficiency of B: B takes thrice as many days as C. Since C takes 6 days to complete the work alone, B takes:
Days taken by B=3×6=18 days
Thus, B's efficiency is:
Efficiency of B=1 work18 days=118 work/day

Step 2: Calculate the total work

The total work can be calculated using A's efficiency:
Total Work=Efficiency of A×Days taken by A=112×12=1 work unit

Step 3: Calculate the work done in pairs

1. Day 1 (A and B):
Work done=Efficiency of A+Efficiency of B=112+118
To add these fractions, find a common denominator (36):
=336+236=536 work units

2. Day 2 (B and C):
Work done=Efficiency of B+Efficiency of C=118+16
Common denominator (18):
=118+318=418=29 work units

3. Day 3 (C and A):
Work done=Efficiency of C+Efficiency of A=16+112
Common denominator (12):
=212+112=312=14 work units

Step 4: Total work done in three days

Now, let's calculate the total work done in three days:
Total work in 3 days=536+29+14
Finding a common denominator (36):
=536+836+936=2236=1118 work units

Step 5: Calculate remaining work and days needed

After 3 days, the remaining work is:
Remaining work=11118=718 work units

Step 6: Work done in the next cycles

1. Day 4 (A and B):
Work done=536
Remaining work after Day 4:
718536=1436536=936=14

2. Day 5 (B and C):
Work done=29
Remaining work after Day 5:
1429=936836=136

3. Day 6 (C and A):
Work done=14
On Day 6, they will complete the remaining work of 136.

Final Calculation of Total Days

Total days taken:
- 5 full days + a fraction of the 6th day.

Thus, the total time taken to complete the work is:
Total Days=6 days

Final Answer
The total number of days required to finish the work is 6 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?

    A4
    B2
    C12
    D16
  • Question 2 - Select One

    A and B together finish a work in 4 day while Aalone finishes the work girl 12 day In how many days will B finish the san work ?

    A5
    B6
    C7
    D8
  • Question 3 - Select One

    A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?

    A18 days
    B21 days
    C24 days
    D27 days