A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
60
80
20
25
The correct Answer is:C
Step by step video, text & image solution for A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 1/2th of the work was still to be done. How many more men were required.to complete the work in stipulated time? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 12th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
A60B80C20D25 - Question 2 - Select One
A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that 13rd of the work was still to be done. How many more men were required to complete the work in stipulated time?
A16B15C20D25 - Question 3 - Select One
10 men can make a wall in 8 days. How many men required to complete the same work in half day
A80B100C120D160
20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.
View SolutionA contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?
View SolutionIf 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View Solution