Doubtnut Promotions Sticky

Progressive Company Pvt. Ltd. hired some employees in a fix pattern. On the first day it hired one person, on second day one more joined him. On the third, fourth etc (i.e every next day) one more person increased in this group. The capacity of each person was same. The whole work was completed on the 24th day then out of total ₹ 5000, maximum how much a person had earned?

A

₹ 500

B

₹ 400

C

₹ 200

D

₹ 250

Video Solution
Text Solution
Verified by Experts

The correct Answer is:B

|
Answer

Step by step video, text & image solution for Progressive Company Pvt. Ltd. hired some employees in a fix pattern. On the first day it hired one person, on second day one more joined him. On the third, fourth etc (i.e every next day) one more person increased in this group. The capacity of each person was same. The whole work was completed on the 24th day then out of total ₹ 5000, maximum how much a person had earned? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Progressive Company Pvt. Ltd. hired some employees in a fix pattern. On the first day it hired one person, on second day one more joined him. On the third, fourth etc (i.e every next day) one more person increased in this group. The capacity of each person was same. The whole work was completed on the 24th day then out of total ₹ 5000, maximum how much a person had earned?

    ARs. 500
    BRs. 400
    CRs. 200
    DRs. 250
  • Question 2 - Select One

    A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work?

    A8 days
    B9 days
    C10 days
    D11 days
  • Question 3 - Select One

    Two persons takes 9 days to complete 2 work. To complete double of that work, in 12 days how many more persons will be required?

    A2
    B3
    C1
    D4