Doubtnut Promotions Sticky

Boston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person?

A

₹ 900

B

₹ 1200

C

₹ 1000

D

none of these

Video Solution
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for Boston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Boston, Churchill and David are three workers, employed by a contractor. They completed the whole work in 10 days. Initially all of them worked together, but the last 60% of the work was completed by only Churchill and David together. Boston worked with Churchill and David only for initial two days then he left the work due to his poor health. Also Churchill takes 20% less time to finish the work alone than that of David working alone. If they were paid ₹ 3000 for the entire work, then what is the share of least efficient person?

    ARs. 900
    BRs. 1200
    CRs. 1000
    Dnone of these
  • Question 2 - Select One

    A man completes a work in 12 days another man completes the same work 10 days. If both work together, then how many days will the work completed ?

    A5
    B5511
    C1/11
    D11
  • Question 3 - Select One

    S and T can finish a work in 50 days. They worked together for 20 days and then left . How much of the work is left

    A3/5
    B1/3
    C1/2
    D2/5