A man working 6 hours a day takes 8 days to complete a project. How many hours a day must he work to complete. It in 3 days?

A

16

B

10

C

20

D

15

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we can follow these instructions:

Step 1: Calculate the total work done
The man works 6 hours a day for 8 days. To find the total work done in hours, we multiply the number of hours worked per day by the number of days worked.

Total work=Hours per day×Number of days=6 hours/day×8 days=48 hours

Step 2: Determine the required hours per day to complete the work in 3 days
Now that we know the total work required is 48 hours, we need to find out how many hours he must work each day to complete this work in 3 days. We do this by dividing the total work by the number of days.

Hours per day=Total workNumber of days=48 hours3 days=16 hours/day

Conclusion
The man must work 16 hours a day to complete the project in 3 days.

---

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 30 persons take 10 days to complete a certain work working 8 hours a day. Then 40 persons should work how many hours a day so that the work is completed in 6 days?
    यदि 30 लोग प्रतिदिन 8 घंटे कार्य करके किसी कार्य को 10 दिनों में पूरा करते हैं, तो इस कार्य को 6 दिनों में पूरा करने के लिए 40 व्यक्ति दिन में कितने घंटे कार्य करेंगे ?

    A6
    B10
    C8
    D12
  • A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?

    A4
    B5411
    C6411
    D4411
  • A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?

    A4
    B5411
    C6411
    D4411