A man working 6 hours a day takes 8 days to complete a project. How many hours a day must he work to complete. It in 3 days?
16
10
20
15
The correct Answer is:C
To solve the problem step by step, we can follow these instructions:
Step 1: Calculate the total work done
The man works 6 hours a day for 8 days. To find the total work done in hours, we multiply the number of hours worked per day by the number of days worked.
Total work=Hours per day×Number of days=6 hours/day×8 days=48 hours
Step 2: Determine the required hours per day to complete the work in 3 days
Now that we know the total work required is 48 hours, we need to find out how many hours he must work each day to complete this work in 3 days. We do this by dividing the total work by the number of days.
Hours per day=Total workNumber of days=48 hours3 days=16 hours/day
Conclusion
The man must work 16 hours a day to complete the project in 3 days.
---
The man works 6 hours a day for 8 days. To find the total work done in hours, we multiply the number of hours worked per day by the number of days worked.
Now that we know the total work required is 48 hours, we need to find out how many hours he must work each day to complete this work in 3 days. We do this by dividing the total work by the number of days.
The man must work 16 hours a day to complete the project in 3 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
If 30 persons take 10 days to complete a certain work working 8 hours a day. Then 40 persons should work how many hours a day so that the work is completed in 6 days?
यदि 30 लोग प्रतिदिन 8 घंटे कार्य करके किसी कार्य को 10 दिनों में पूरा करते हैं, तो इस कार्य को 6 दिनों में पूरा करने के लिए 40 व्यक्ति दिन में कितने घंटे कार्य करेंगे ?A6B10C8D12 - Question 2 - Select One
A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?
A4B5411C6411D4411 - Question 3 - Select One
A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?
A4B5411C6411D4411
10 men, working. 6 hours a day can compJete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?
View SolutionFifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View SolutionFifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View SolutionWorking 6 hours a day, Raman can complete a piece of work in 24 days. How many hours a day should he work so as to finish the work in 18 days?
View Solution