Doubtnut Promotions Sticky

A can do 2 5 of a work in 6 days and B can do 2 3 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

A

12 days

B

9 days

C

10 days

D

8 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in: by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Knowledge Check

  • Question 1 - Select One

    A can finish 35 of a task in 6 days and B can finish 23 of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. If B and C working together will complete the same task in:

    A10 days
    B18 days
    C12 days
    D15 days
  • Question 1 - Select One

    A can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

    A15 days
    B10 days
    C18 days
    D12 days
  • Question 1 - Select One

    A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days
  • Question 1 - Select One

    A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

    A8 days
    B5 days
    C4 days
    D6 days
  • Question 1 - Select One

    A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :

    A212 days
    B3 days
    C112 days
    D2 days
  • Question 1 - Select One

    A can do 35th of a work in 12 days, B can do 13rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?

    A9 days
    B6 days
    C4 days
    D5 days
  • Question 1 - Select One

    A can do 12 of a work in 9 days while B can do 13 of the same same work in 6 days. How long would it take for A and B together to complete the work?

    A8 days
    B9 days
    C10 days
    D7 days
  • Question 1 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • Question 1 - Select One

    A can complete one-third of a work in 10 days and B can do 35th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do 23 of the same work?

    ARs. 12,800
    BRs. 12,500
    CRs. 13,200
    DRs. 12,000

Similar Questions