A contract of construction job specifies a penalty for delay of completion beyond a certain date as follows:₹200 for the first day,₹250 for the second day,₹300 for the thrid day etc.the penalty for each succeeding day being ₹50 more than for the preceding day.How much does a delay of 30 days cost the contractor?Solution in Assamese

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A contract of construction job specifies a penalty for delay of completion beyond a certain date as follows:₹200 for the first day,₹250 for the second day,₹300 for the thrid day etc.the penalty for each succeeding day being ₹50 more than for the preceding day.How much does a delay of 30 days cost the contractor? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions