A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows : $200 for the first day, $250 for the second day, $ 300 for the third day, etc., the penalty for each succeeding day being $50 more than for the preceding day, How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ?Solution in Punjabi
Step by step video & image solution for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows : $200 for the first day, $250 for the second day, $ 300 for the third day, etc., the penalty for each succeeding day being $50 more than for the preceding day, How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Topper's Solved these Questions
Similar Questions
Find out which of the following sequences are arithmetic progressions. For those which are arithmetic progressions, find out the common difference. :- 3,6,12,24,….
05:31View SolutionA bicycle wheel makes 500 revolutions in moving 11 km. Find the diameter of the wheel.
04:10View SolutionComplete the prime factor tree :
02:52View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty?
04:07View SolutionA contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day,Rs.250 for second day,Rs.300 for thirdday and so on.If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed.
03:04View Solutionनिर्माण कार्य से संबंधित किसी ठेके में, एक निश्चित तिथि के बाद कार्य को विलम्ब से पूरा करने के लिए, जुर्माना लगाने का प्रावधान इस प्रकार हैं : पहले दिन के लिए ₹ 200, दूसरे दिन के लिए ₹ 250, तीसरे दिन के लिए ₹ 300 इत्यादि, अर्थात प्रत्येक उत्तरोत्तर दिन का जुर्माना अपने से ठीक पहले दिन के जुर्माने से ₹50 अधिक हैं । एक ठेकेदार को जुर्माने के रूप में कितनी राशि अदा करनी पड़ेगी, यदि वह इस कार्य में 30 दिन का विलम्ब कर देता हैं?
05:26View Solutionनिर्माण कार्य से सम्बंधित किसी ठेके में, एक निश्चित तिथि के बाद के कार्य को बिलम्ब से पूरा करने के लिए, जुर्माना लगाने का प्रावधान इस प्रकार है पहले दिन के लिए Rs.200 दूसरे दिन के लिए Rs.250, तीसरे दिन के लिए Rs. 300 इत्यादि, अर्थात प्रत्येक उत्तरोत्तर दिन का जुर्माना अपने से ठीक पहले दिन के जुर्माना से Rs. 50 अधिक है । एक ठेकेदार को जुर्माना के रूप में कितनी राशि अदा करनी पड़ेगी, यदि वह इस कार्य में 30 दिन का बिलम्ब कर देता है ?
04:16View Solutionनिर्माण कार्य से संबंधित किसी ठेके में, एक निश्चित तिथि के बाद कार्य को विलम्ब सेपूरा करने के लिए, जुर्माना लगाने का प्रावधान इस प्रकार है: पहले दिन के लिए रू0 200, दूसरे दिन के लिए रू0 250, तीसरे दिन के लिए रू0 300 इत्यादि। अर्थात प्रत्येक उत्तरोत्तर दिन का जुर्माना अपने से ठीक पहले दिन के जुर्माने से रू0 50 अधिक है। एक ठेकेदार को जुर्माने के रूप में कितनी राशि अदा करनी पड़ेगी, यदि वह इस कार्य को 30 दिन में विलम्ब से पूरा करता है?
04:04View SolutionA construction company will be penalised each day for delay in construction of a bridge. The penalty will be Rs 4000 for the first day and will increase by Rs 1000 for each following day. Based on its budget, the company can afford to pay a maximum of Rs 1,65,000 towards penalty. Find the maximum number of days by which the construction of work can be delayed.
04:19View SolutionIf the work of a building is completed late after a certain amount of time, that is. The form was fined. It is as follows: Rs.200 for first day, Rs.250 for second day, Rs.300 for 3rd day. Every day. The penalty is' Rs.50 a pound higher than the previous day's fine. If a contractor takes more than 30 days to complete a job, calculate the penalty he must pay?
03:52View SolutionA can do a job in 15 days, B in 10 days and C in 30 days. If A is helped by B and C on every third day, then the job will be completed in
06:04View Solutionਨਿਰਮਾਣ ਕਾਰਜ ਨਾਲ ਸਬੰਧਤ ਕਿਸੇ ਠੇਕੇ ਵਿੱਚ ਕਿਸੇ ਨਿਸ਼ਚਿਤ ਮਿਤੀ ਤੋਂ ਬਾਅਦ ਕੰਮ ਦੇਰੀ ਨਾਲ ਪੂਰਾ ਕਰਨ ਲਈ, ਜੂਰਮਾਨਾ ਲਗਾਉਣ ਦੀ ਵਿਵਸਥਾ ਇਸ ਪ੍ਰਕਾਰ ਹੈ ਪਹਿਲੇ ਦਿਨ ਦੇ ਲਈ Rs 200 ਦੂਸਰੇ ਦਿਨ ਲਈ Rs 250 ਤੀਸਰੇ ਦਿਨ ਲਈ Rs 300 ਆਦਿ ਭਾਵ ਹਰੇਕ ਅਗਲੇ ਦਿਨ ਦਾ ਜੁਰਮਾਨਾ ਆਪਣੇ ਤੋਂ ਠੀਕ ਪਹਿਲੇ ਦਿਨ ਦੇ ਜੁਰਮਾਨੇ ਨਾਲੋਂ Rs 50 ਵੱਧ ਹੈ। ਇੱਕ ਠੇਕੇਦਾਰ ਨੂੰ ਜੁਰਮਾਨੇ ਦੇ ਰੂਪ ਵਿੱਚ ਕਿੰਨੀ ਰਕਮ ਦੇਣੀ ਪਵੇਗੀ, ਜੇਕਰ ਉਹ ਇਸ ਕੰਮ ਵਿੱਚ 30 ਦਿਨ ਦੀ ਦੇਰੀ ਕਰ ਦਿੰਦਾ ਹੈ?
07:50View SolutionA contract of construction job specifies a penalty for delay of completion beyond a certain date as follows:₹200 for the first day,₹250 for the second day,₹300 for the thrid day etc.the penalty for each succeeding day being ₹50 more than for the preceding day.How much does a delay of 30 days cost the contractor?
03:46View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date is as follows,
₹200 for 1st day,₹250 for 2nd day,₹300 for 3rd day and so on.If the contractor pays 27,750 as penalty,find the number of days for which the work is delayed.03:21View SolutionA contractor construction job specifies a penalty for delay of completion beyond a certain date as follow. Rs. 200 for the first day. The penalty for each succeeding day being Rs. 50 more than the preceding day. How much money does the contractor pay as penalty if he has delayed the work by 30 days?
01:58View SolutionThe total wages for completing one work is Rs 640. A and B can separately do that work in 8 days and 12 days respectively but they finish the work in alternate days i.e. on first day B, second day A, again on third day A and so on. As the work goes on, how much money did A get?
03:49View Solution