A can complete a work in 20 days and B, in 30 days. A worked alone for 4 days and B completed the remaining work along with C in 18 days. In how many days 'C’ can working, alone complete the work?
A किसी काम को 20 दिन में समाप्त कर सकता है, और B, 30 दिन में, A अकेला 4 दिन तक काम करता है, और शेष कार्य B, C के साथ मिलकर 18 दिन में करता है। C अकेला उस काम को कितने दिन में कर सकता है।
72
90
12
68
To solve the problem, we will follow these steps:
Step 1: Determine the work done by A and B
A can complete the work in 20 days, which means A's work rate is:
Work rate of A=120 (work per day)
B can complete the work in 30 days, which means B's work rate is:
Work rate of B=130 (work per day)
Step 2: Calculate the total work in terms of units
Let's assume the total work is 60 units (this is a common multiple of 20 and 30, making calculations easier).
Step 3: Calculate the work done by A in 4 days
In 4 days, A will complete:
Work done by A in 4 days=4×6020=12 units
Step 4: Calculate the remaining work
The remaining work after A has worked for 4 days is:
Remaining work=60−12=48 units
Step 5: Work done by B and C together
B and C complete the remaining 48 units of work in 18 days. Let C's work rate be 1x (where x is the number of days C takes to complete the work alone). The combined work rate of B and C is:
Work rate of B and C=130+1x
Step 6: Set up the equation for work done in 18 days
The total work done by B and C in 18 days is:
18(130+1x)=48
Step 7: Solve the equation
Expanding the equation:
1830+18x=48
35+18x=48
Subtract 35 from both sides:
18x=48−35
Convert 48 to a fraction:
48=2405
So:
18x=2405−35=2375
Cross-multiplying gives:
18⋅5=237x
90=237x
x=90237=3079 days
Step 8: Calculate the total time C would take to complete the work alone
To find out how many days C would take to complete the entire work alone, we use:
Total work=60 units
C's work rate=1x=7930
Thus, the time taken by C alone to complete the work is:
Time taken by C=607930=60⋅3079=180079≈22.78 days
Final Answer
C can complete the work alone in approximately 22.78 days.
A can complete the work in 20 days, which means A's work rate is:
Work rate of A=120 (work per day)
Work rate of B=130 (work per day)
Let's assume the total work is 60 units (this is a common multiple of 20 and 30, making calculations easier).
In 4 days, A will complete:
Work done by A in 4 days=4×6020=12 units
The remaining work after A has worked for 4 days is:
Remaining work=60−12=48 units
B and C complete the remaining 48 units of work in 18 days. Let C's work rate be 1x (where x is the number of days C takes to complete the work alone). The combined work rate of B and C is:
Work rate of B and C=130+1x
The total work done by B and C in 18 days is:
18(130+1x)=48
Expanding the equation:
1830+18x=48
35+18x=48
Subtract 35 from both sides:
18x=48−35
Convert 48 to a fraction:
48=2405
So:
18x=2405−35=2375
Cross-multiplying gives:
18⋅5=237x
90=237x
x=90237=3079 days
To find out how many days C would take to complete the entire work alone, we use:
Total work=60 units
C's work rate=1x=7930
Thus, the time taken by C alone to complete the work is:
Time taken by C=607930=60⋅3079=180079≈22.78 days
C can complete the work alone in approximately 22.78 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?
A12B68C72D90 - Question 2 - Select One
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62 - Question 3 - Select One
A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA and B together can do a piece work in 20 days. B and C together can do the same work in 25 days. C and A together can do the same work in 15 days. In how many days A alone can do the work?
A तथा B मिलकर किसी कार्य को 20 दिन में कर सकते हैं | B तथा C मिलकर उसी कार्य को 25 दिन में कर सकते हैं | C तथा A मिलकर उसी कार्य को 15 दिन में कर सकते हैं | A अकेला उस कार्य को कितने दिनों में कर सकता है?View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View SolutionBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
View Solution