Doubtnut Promotions Sticky

A and B each working alone can do a work in 15 days and 25 days respectivley. They started the work together, but B left after some time and A finished the remaining work in 7 days. After how many days form the start did B leave?
A और B अकेले किसी काम को क्रमशः 15 और 25 दिन में कर सकते है, उन्होंने मिलकर काम शुरू किया परन्तु B कुछ समय बाद चला जाता है, और A शेष काम को 7 दिन मे समाप्त करता है। प्रारंभ में B ने कितने दिनों बाद काम छोंड दिया?

A

7

B

9

C

3

D

5

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will determine how long B worked before leaving and how much work A completed afterward.

Step 1: Determine the total work
A can complete the work in 15 days, and B can complete it in 25 days. To find the total work, we can use the formula:
Total Work=LCM of (15, 25)
The LCM of 15 and 25 is 75. Therefore, the total work is 75 units.

Step 2: Calculate the efficiencies of A and B
Now, we calculate the daily work done by A and B:
- A's efficiency = Total Work / Days taken by A = 75/15=5 units/day
- B's efficiency = Total Work / Days taken by B = 75/25=3 units/day

Step 3: Calculate the combined efficiency of A and B
When A and B work together, their combined efficiency is:
Combined Efficiency=AsEfficiency+BsEfficiency=5+3=8 units/day

Step 4: Calculate the work done by A and B together before B leaves
Let x be the number of days A and B worked together. In x days, the amount of work done by both A and B is:
Work done together=Combined Efficiency×x=8x units

Step 5: Calculate the remaining work done by A
After B leaves, A finishes the remaining work in 7 days. The amount of work A can complete in 7 days is:
Work done by A in 7 days=AsEfficiency×7=5×7=35 units

Step 6: Set up the equation for total work
The total work done can be expressed as:
Total Work=Work done together+Work done by A in 7 days
Substituting the known values:
75=8x+35

Step 7: Solve for x
Rearranging the equation gives:
8x=7535
8x=40
x=5

Conclusion
B left after 5 days from the start.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?

    A3
    B5
    C7
    D9
  • Question 2 - Select One

    Raja and Baja working alone can do a work in 20 days and 15 days respectively. They stared the work together but Baja left after sometime and Raja finished remaining work in 6 days. Find after how many days from start Baja left the work?

    A5 days
    B4 days
    C6 days
    D3 days
  • Question 3 - Select One

    A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

    A2 days
    B3 days
    C1 day
    DNone of these