A and B each working alone can do a work in 15 days and 25 days respectivley. They started the work together, but B left after some time and A finished the remaining work in 7 days. After how many days form the start did B leave?
A और B अकेले किसी काम को क्रमशः 15 और 25 दिन में कर सकते है, उन्होंने मिलकर काम शुरू किया परन्तु B कुछ समय बाद चला जाता है, और A शेष काम को 7 दिन मे समाप्त करता है। प्रारंभ में B ने कितने दिनों बाद काम छोंड दिया?
7
9
3
5
To solve the problem step by step, we will determine how long B worked before leaving and how much work A completed afterward.
Step 1: Determine the total work
A can complete the work in 15 days, and B can complete it in 25 days. To find the total work, we can use the formula:
Total Work=LCM of (15, 25)
The LCM of 15 and 25 is 75. Therefore, the total work is 75 units.
Step 2: Calculate the efficiencies of A and B
Now, we calculate the daily work done by A and B:
- A's efficiency = Total Work / Days taken by A = 75/15=5 units/day
- B's efficiency = Total Work / Days taken by B = 75/25=3 units/day
Step 3: Calculate the combined efficiency of A and B
When A and B work together, their combined efficiency is:
Combined Efficiency=A′sEfficiency+B′sEfficiency=5+3=8 units/day
Step 4: Calculate the work done by A and B together before B leaves
Let x be the number of days A and B worked together. In x days, the amount of work done by both A and B is:
Work done together=Combined Efficiency×x=8x units
Step 5: Calculate the remaining work done by A
After B leaves, A finishes the remaining work in 7 days. The amount of work A can complete in 7 days is:
Work done by A in 7 days=A′sEfficiency×7=5×7=35 units
Step 6: Set up the equation for total work
The total work done can be expressed as:
Total Work=Work done together+Work done by A in 7 days
Substituting the known values:
75=8x+35
Step 7: Solve for x
Rearranging the equation gives:
8x=75−35
8x=40
x=5
Conclusion
B left after 5 days from the start.
A can complete the work in 15 days, and B can complete it in 25 days. To find the total work, we can use the formula:
Total Work=LCM of (15, 25)
The LCM of 15 and 25 is 75. Therefore, the total work is 75 units.
Now, we calculate the daily work done by A and B:
- A's efficiency = Total Work / Days taken by A = 75/15=5 units/day
- B's efficiency = Total Work / Days taken by B = 75/25=3 units/day
When A and B work together, their combined efficiency is:
Combined Efficiency=A′sEfficiency+B′sEfficiency=5+3=8 units/day
Let x be the number of days A and B worked together. In x days, the amount of work done by both A and B is:
Work done together=Combined Efficiency×x=8x units
After B leaves, A finishes the remaining work in 7 days. The amount of work A can complete in 7 days is:
Work done by A in 7 days=A′sEfficiency×7=5×7=35 units
The total work done can be expressed as:
Total Work=Work done together+Work done by A in 7 days
Substituting the known values:
75=8x+35
Rearranging the equation gives:
8x=75−35
8x=40
x=5
B left after 5 days from the start.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View Solution
Knowledge Check
- Question 1 - Select One
A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?
A3B5C7D9 - Question 2 - Select One
Raja and Baja working alone can do a work in 20 days and 15 days respectively. They stared the work together but Baja left after sometime and Raja finished remaining work in 6 days. Find after how many days from start Baja left the work?
A5 daysB4 daysC6 daysD3 days - Question 3 - Select One
A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
A2 daysB3 daysC1 dayDNone of these
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B cand o a pieces of work in 10 days and 15 days, respectively. They started the work together but B left after sometime and A finished the work in 5 days. After how many days (from the start) did B leave?
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some das and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View Solution