How many men will be required to plough 50 acres of land in 10 days if 15 men required 6 days to plough 10 acres of land?
अगर 10 आदमियों को 10 एकड़ ज़मीन जोतने के लिए 15 दिन की ज़रूरत होती है तो 10 दिनों में 50 एकड़ ज़मीन जोतने के लिए कितने आदमियों की ज़रूरत होगी?
45
40
55
50
To solve the problem, we need to determine how many men are required to plough 50 acres of land in 10 days, given that 15 men can plough 10 acres in 6 days. We can use the concept of work done, which can be expressed as:
Men×Days=Work
Step 1: Calculate the total work done by 15 men in 6 days.
The work done (in acres) can be calculated as:
Work=Number of Men×Number of Days
For the first scenario:
Work=15 men×6 days=90 man-days
This 90 man-days corresponds to 10 acres of land.
Step 2: Calculate the work done per acre.
To find out how many man-days are required to plough one acre, we divide the total man-days by the number of acres:
Man-days per acre=90 man-days10 acres=9 man-days per acre
Step 3: Calculate the total man-days required for 50 acres.
Now, we need to find the total man-days required to plough 50 acres:
Total man-days for 50 acres=50 acres×9 man-days per acre=450 man-days
Step 4: Determine the number of men required to complete the work in 10 days.
We know that the total work required is 450 man-days and the work needs to be completed in 10 days. Therefore, we can find the number of men required (M) using the formula:
M=Total man-daysNumber of Days=450 man-days10 days=45 men
Final Answer:
Thus, the number of men required to plough 50 acres of land in 10 days is 45 men.
---
The work done (in acres) can be calculated as:
Work=Number of Men×Number of Days
For the first scenario:
Work=15 men×6 days=90 man-days
This 90 man-days corresponds to 10 acres of land.
To find out how many man-days are required to plough one acre, we divide the total man-days by the number of acres:
Man-days per acre=90 man-days10 acres=9 man-days per acre
Now, we need to find the total man-days required to plough 50 acres:
Total man-days for 50 acres=50 acres×9 man-days per acre=450 man-days
We know that the total work required is 450 man-days and the work needs to be completed in 10 days. Therefore, we can find the number of men required (M) using the formula:
M=Total man-daysNumber of Days=450 man-days10 days=45 men
Thus, the number of men required to plough 50 acres of land in 10 days is 45 men.
Topper's Solved these Questions
Similar Questions
How many men will be required to plough 100acres of a land in 10days if 10men require 8days of plough 20acres of land?
View SolutionIf 15 men can do a piece of work in 14 days, how many men will be needed to do the work in 30 days?
यदि 15 लोग किसी कार्य को 14 दिनों में कर सकते हैं, तो इस कार्य को 30 दिनों में करने के लिए कितने लोगों की आवश्यकता होगी ?View Solution
Knowledge Check
- Question 1 - Select One
Twenty men can lay a road off 50 km long in 10 days. In how many days can 15 men lay a road of 75 km long?
A10 daysB20 daysC30 daysD40 days - Question 2 - Select One
Twenty men can lay a road off 50 km long in 10 days. In how many days can 15 men lay a road of 75 km long?
A10 daysB20 daysC30 daysD40 days - Question 3 - Select One
36 men together can build a wall 140m long in 21 days, the number of men working at the same rate required to build the same wall in 14 days is
36 आदमी मिलकर 140 मीटर लम्बी दीवार 21 दिन में बना सकते हैं, यदि वह दीवार 14 दिन में उसी औसत से बनाई जानी हो तो कितने आदमियों की आवश्यकता होगी?A54B48C36D18
24 persons working 8 hours a day can complete 2 units of a work in 10 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
एक दिन में 8 घंटे कार्य करते हुए 24 व्यक्ति किसी कार्य की 2 इकाई 10 दिनों में समाप्त कर सकते हैं | इस कार्य की 4 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी यदि वे 16 दिनों तक एक दिन में 6 घंटे कार्य करते हैं ?View Solution6 men can repair a road in 14 hours. How many men will be required to repair the road in 4 hours?
6 पुरुष किसी सड़क की मरम्मत 14 घंटों में कर सकते हैं | 4 घंटों में सड़क की मरम्मत करने के लिए कितने पुरुषों की आवश्यकता होगी?View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
एक दिन में 8 घंटे कार्य करते हुए 18 व्यक्ति किसी कार्य की 3 इकाई 10 दिनों में समाप्त कर सकते हैं | प्रतिदिन 6 घंटे कार्य करते हुए 16 दिन में इस कार्य की 5 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी ?View Solution36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?
प्रतिदिन 8 घंटे कार्य करके 36 लोग किसी कार्य की 3 इकाई 12 दिनों में कर सकते हैं| यदि वे एक दिन में 6 घंटे कार्य करें तो 16 दिन में इस कार्य की 5 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी ?View Solution240 men can finish a work in 20 days working 5 hours a day. To finish the work within 10 days working 8 hours a day, the minimum number of men required is
240 आदमी प्रतिदिन 5 घंटे काम करके एक काम को 20 दिन में पूरा कर सकते है। उसी काम को प्रतिदिन 8 घंटे काम करके 10 दिन के भीतर पूरा करने के लिए अपेक्षित आदमियों की न्यूनतम संख्या है-View Solution