A and B separately can build a wall in 12 days and 16 days, respectively. If they work alternatively, starting with A, in how many days will the wall be built?
A और B अलग-अलग क्रमशः 12 दिनों और 16 दिनों में एक दीवार का निर्माण कर सकते हैं। यदि वे एक दिन छोड़कर कार्य करते हैं, तो A से शुरू करके, कितने दिनों में दीवार बनाई जाएगी?
723 days
1223 days
1323 days
634 days
To solve the problem step by step, we will follow the approach outlined in the video transcript.
Step 1: Determine the Total Work
We need to find the total work that needs to be done to build the wall. This can be calculated using the Least Common Multiple (LCM) of the days taken by A and B to complete the work individually.
- A can build the wall in 12 days.
- B can build the wall in 16 days.
LCM of 12 and 16:
- The prime factorization of 12 is 22×31.
- The prime factorization of 16 is 24.
- The LCM is obtained by taking the highest power of each prime factor:
- 24 (from 16) and 31 (from 12).
Thus, LCM = 24×31=16×3=48.
Total Work = 48 units.
Step 2: Calculate A's and B's Work Per Day
Next, we calculate how much work A and B can do in one day.
- A's work per day:
A′swork=TotalWorkDaystakenbyA=4812=4unitsperday.
- B's work per day:
B′swork=TotalWorkDaystakenbyB=4816=3unitsperday.
Step 3: Calculate Work Done in Two Days
Since A and B work alternately starting with A, we need to calculate how much work is done in a cycle of two days.
- Day 1 (A works): 4 units
- Day 2 (B works): 3 units
Total work in 2 days = 4 + 3 = 7 units.
Step 4: Calculate Total Days to Complete the Work
Now, we need to find out how many complete cycles of 2 days it takes to complete the total work of 48 units.
- Number of complete cycles:
Complete cycles=TotalWorkWorkin2days=487≈6.857.
This means there are 6 complete cycles (which take 6×2=12 days) and some work left.
Step 5: Calculate Remaining Work
After 12 days, the work done is:
Work done in 12 days=6×7=42units.
Remaining work = Total Work - Work done = 48 - 42 = 6 units.
Step 6: Determine Who Works Next
After 12 days, it is A's turn to work again.
- A's work on Day 13: A can complete 4 units in one day, but only 6 units are left.
- Since A can complete 4 units, after Day 13, the remaining work will be:
6−4=2units.
Step 7: Calculate Time Taken by B to Complete Remaining Work
Now, it will be B's turn to work on Day 14.
- B's work on Day 14: B can complete 3 units in one day. However, only 2 units are left.
Time taken by B to complete 2 units:
Time=RemainingWorkB′sworkperday=23days.
Step 8: Calculate Total Time Taken
Finally, we add up all the days worked:
Total Time=12days+1day(Day13)+23day(Day14)=13+23days.
Thus, the total time taken to build the wall is:
Total Time=1323days.
Final Answer
The wall will be built in 13 23 days.
We need to find the total work that needs to be done to build the wall. This can be calculated using the Least Common Multiple (LCM) of the days taken by A and B to complete the work individually.
- B can build the wall in 16 days.
- The prime factorization of 12 is 22×31.
- The prime factorization of 16 is 24.
- The LCM is obtained by taking the highest power of each prime factor:
- 24 (from 16) and 31 (from 12).
Thus, LCM = 24×31=16×3=48.
Next, we calculate how much work A and B can do in one day.
A′swork=TotalWorkDaystakenbyA=4812=4unitsperday.
B′swork=TotalWorkDaystakenbyB=4816=3unitsperday.
Since A and B work alternately starting with A, we need to calculate how much work is done in a cycle of two days.
- Day 2 (B works): 3 units
Now, we need to find out how many complete cycles of 2 days it takes to complete the total work of 48 units.
Complete cycles=TotalWorkWorkin2days=487≈6.857.
After 12 days, the work done is:
Work done in 12 days=6×7=42units.
After 12 days, it is A's turn to work again.
- Since A can complete 4 units, after Day 13, the remaining work will be:
6−4=2units.
Now, it will be B's turn to work on Day 14.
Time=RemainingWorkB′sworkperday=23days.
Finally, we add up all the days worked:
Total Time=12days+1day(Day13)+23day(Day14)=13+23days.
Total Time=1323days.
The wall will be built in 13 23 days.
Topper's Solved these Questions
Similar Questions
Smith and Ajit can complete a task in 12 days and 18 days respectively. If they work together on a task for 4 days, then the fraction of task that will be left is:
स्मिथ और अजीत क्रमशः 12 दिनों और 18 दिनों में एक कार्य पूरा कर सकते हैं। यदि वे 4 दिनों के लिए एक कार्य पर एक साथ कार्य करते हैं, तो जो कार्य शेष होगा वह है:
View SolutionP and Q can finish a work in 10 days and 5 days, respectively. Q worked for 2 days and left the job. In how many days can P alone finish the remaining work?
P और Qक्रमशः 10 दिनों और 5 दिनों में एक कार्य खत्म कर सकते हैं। Q ने 2 दिन कार्य किया और नौकरी छोड़ दी। P शेष कार्य को कितने दिनों में पूरा कर सकता है?
View SolutionAmir and Akbar can finish a task in 30 days and 15 days, respectively. Akbar worked on the task for 8 days and left the job. In how many days can Amir alone finish the remaining work?
आमिर और अकबर क्रमशः 30 दिनों और 15 दिनों में एक कार्य पूरा कर सकते हैं। अकबर ने 8 दिनों तक कार्य किया और नौकरी छोड़ दी। शेष कार्य को आमिर अकेले कितने दिनों में पूरा कर सकता है?
View SolutionA and B can do a work in 15 days and 10 days respectively. They begin the work together but B leaves after two days. Now A completes the remaining work. The total number of days needed for the completion of the work is:
A और B क्रमशः 15 दिनों और 10 दिनों में एक कार्य कर सकते हैं। वे एक साथ कार्य शुरू करते हैं लेकिन B दो दिनों के बाद छोड़ देता हैं। अब A शेष कार्य को पूरा करता है। कार्य पूरा होने के लिए आवश्यक कुल दिनों की संख्या है:
View SolutionA and B can complete a piece of work in 20 days and 30 days respectively. A works full time while B works half of the time. In how many days the entire work will be completed?
A तथा B किसी कार्य को क्रमशः 20 दिनों तथा 30 दिनों में पूरा कर सकते हैं | A पूरे समय कार्य करता है जबकि B आधे समय कार्य करता है | पूरा कार्य कितने दिनों में समाप्त हो जाएगा?
View SolutionA, B and C can do work separately in 18,36 and 54 days respectively. They started the work together, but B and C left 5 days and 10 days, respectively, before the completion of the work. In How many days was the work finished?
A, B और C अलग-अलग क्रमश 18, 36 और 54 दिनों में एक कार्य कर सकते हैं। उन्होंने एक साथ कार्य शुरू किया, लेकिन B और C ने कार्य पूरा होने से क्रमश: 5 दिन और 10 दिन पहले छोड़ दिया। कितने दिनों में कार्य पूरा हो गया था?
View SolutionA, B and C can complete a piece of work in 20, 24 and 36 days respectively. Working together, they can complete the same work in how many days ?
A, B और C किसी कार्य को क्रमशः 20, 24 और 36 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे इसी कार्य को कितने दिनों में पूरा करेंगे ?
View SolutionA and B can do a piece of work alone in 15 and 30 days respectively. In how many days can they together complete the work ?
A और B क्रमशः 15 और 30 दिनों में अकेले किसी काम को पूरा कर सकते हैं। वे कितने दिनों में एक साथ मिलकर इस काम पूरा कर सकते हैं?
View SolutionA, B and C together can build a wall in 12 days. C is four times as productive as B and A alone can build the wall in 48 days. In how many days A and B working together can build the wall?
A, B और C एक साथ 12 दिनों में दीवार बना सकते हैं। B की तुलना में C चार गुना अधिक उत्पादन करता है और A अकेले 48 दिनों में दोवार बना सकता हैं। A और B एक साथ काम करके बाद वह दीवार कितने दिनों में बना सकते हैं?
View SolutionA, B and C can complete a piece of work in 4, 20 and 60 days respectively. Working together, they can complete the one third work in how many days ?
A, B और C किसी कार्य को क्रमशः 4, 20 और 60 दिनों में पूरा कर सकते हैं | एक साथ कार्य करते हुए, वे एक तिहाई कार्य कितने दिनों में समाप्त करेंगे ?
View Solution