A and B separately can build a wall in 12 days and 16 days, respectively. If they work alternatively, starting with A, in how many days will the wall be built?
A और B अलग-अलग क्रमशः 12 दिनों और 16 दिनों में एक दीवार का निर्माण कर सकते हैं। यदि वे एक दिन छोड़कर कार्य करते हैं, तो A से शुरू करके, कितने दिनों में दीवार बनाई जाएगी?

A

723 days

B

1223 days

C

1323 days

D

634 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow the approach outlined in the video transcript.

Step 1: Determine the Total Work
We need to find the total work that needs to be done to build the wall. This can be calculated using the Least Common Multiple (LCM) of the days taken by A and B to complete the work individually.

- A can build the wall in 12 days.
- B can build the wall in 16 days.

LCM of 12 and 16:
- The prime factorization of 12 is 22×31.
- The prime factorization of 16 is 24.
- The LCM is obtained by taking the highest power of each prime factor:
- 24 (from 16) and 31 (from 12).

Thus, LCM = 24×31=16×3=48.

Total Work = 48 units.

Step 2: Calculate A's and B's Work Per Day
Next, we calculate how much work A and B can do in one day.

- A's work per day:
Aswork=TotalWorkDaystakenbyA=4812=4unitsperday.

- B's work per day:
Bswork=TotalWorkDaystakenbyB=4816=3unitsperday.

Step 3: Calculate Work Done in Two Days
Since A and B work alternately starting with A, we need to calculate how much work is done in a cycle of two days.

- Day 1 (A works): 4 units
- Day 2 (B works): 3 units

Total work in 2 days = 4 + 3 = 7 units.

Step 4: Calculate Total Days to Complete the Work
Now, we need to find out how many complete cycles of 2 days it takes to complete the total work of 48 units.

- Number of complete cycles:
Complete cycles=TotalWorkWorkin2days=4876.857.

This means there are 6 complete cycles (which take 6×2=12 days) and some work left.

Step 5: Calculate Remaining Work
After 12 days, the work done is:
Work done in 12 days=6×7=42units.

Remaining work = Total Work - Work done = 48 - 42 = 6 units.

Step 6: Determine Who Works Next
After 12 days, it is A's turn to work again.

- A's work on Day 13: A can complete 4 units in one day, but only 6 units are left.
- Since A can complete 4 units, after Day 13, the remaining work will be:
64=2units.

Step 7: Calculate Time Taken by B to Complete Remaining Work
Now, it will be B's turn to work on Day 14.

- B's work on Day 14: B can complete 3 units in one day. However, only 2 units are left.

Time taken by B to complete 2 units:
Time=RemainingWorkBsworkperday=23days.

Step 8: Calculate Total Time Taken
Finally, we add up all the days worked:
Total Time=12days+1day(Day13)+23day(Day14)=13+23days.

Thus, the total time taken to build the wall is:
Total Time=1323days.

Final Answer
The wall will be built in 13 23 days.

|


Topper's Solved these Questions


Similar Questions