A job can be completed by 6 men and 8 women in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.
4 days
6 days
2 days
8 days
The correct Answer is:A
To solve the problem step by step, we need to establish the work rates of men and women based on the information given in the question.
Step 1: Determine the total work done by 6 men and 8 women in 10 days.
Let the work done by 1 man in 1 day be M and the work done by 1 woman in 1 day be W.
From the first condition:
- 6 men and 8 women can complete the work in 10 days.
The total work W can be expressed as:
W=(6M+8W)×10
Step 2: Determine the total work done by 26 men and 48 women in 2 days.
From the second condition:
- 26 men and 48 women can complete the work in 2 days.
The total work W can also be expressed as:
W=(26M+48W)×2
Step 3: Set the two expressions for total work equal to each other.
From Step 1 and Step 2, we have:
(6M+8W)×10=(26M+48W)×2
Step 4: Simplify the equation.
Expanding both sides:
60M+80W=52M+96W
Rearranging gives:
60M−52M=96W−80W
8M=16W
Step 5: Find the ratio of men to women.
Dividing both sides by 8:
M=2W
This means the ratio of men to women is:
MW=21
Step 6: Use the ratio to find the work done by 15 men and 20 women.
Now we need to find out how many days it will take for 15 men and 20 women to complete the work.
Using the ratio M=2W:
- Work done by 15 men in one day is 15M=15×2W=30W.
- Work done by 20 women in one day is 20W.
Thus, the total work done by 15 men and 20 women in one day is:
30W+20W=50W
Step 7: Calculate the total work W.
From the first condition, we can find W:
W=(6M+8W)×10
Substituting M=2W:
W=(6×2W+8W)×10
W=(12W+8W)×10=20W×10=200W
Step 8: Calculate the number of days for 15 men and 20 women to complete the work.
Now, we can find the number of days D it takes for 15 men and 20 women to complete the work:
D=Total WorkWork per day=200W50W=4 days
Final Answer:
The number of days it will take for 15 men and 20 women to complete the work is 4 days.
---
- 6 men and 8 women can complete the work in 10 days.
W=(6M+8W)×10
- 26 men and 48 women can complete the work in 2 days.
W=(26M+48W)×2
(6M+8W)×10=(26M+48W)×2
60M+80W=52M+96W
60M−52M=96W−80W
8M=16W
M=2W
MW=21
- Work done by 15 men in one day is 15M=15×2W=30W.
- Work done by 20 women in one day is 20W.
30W+20W=50W
W=(6M+8W)×10
Substituting M=2W:
W=(6×2W+8W)×10
W=(12W+8W)×10=20W×10=200W
D=Total WorkWork per day=200W50W=4 days
The number of days it will take for 15 men and 20 women to complete the work is 4 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 women will do the same work in how many days ?
A10 daysB12 daysC13 daysD15 days - Question 2 - Select One
If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 women will do the same work in how many days ?
A10 daysB12 daysC13 daysD15 days - Question 3 - Select One
In how manu days can the work be done by 9 men and 15 women ?
(i) 6 men and 5 women can complete the cork in 6 days.
(ii) 3 men and 4 women can complete the work in 10 days
(iii) 18 men and 15 women can complete the work in 2 days.A(iii) onlyBAll (i), (ii) and (iii)CAny twoDAny one
6 men or 8 women can do a job in 10 days In how many days can 5 men and 9 women do the same job?
View Solution6 men and 8 women can do a work in 10 days.Then, 3 men and 4 women can do the same work in (A) 24 days (B) 20 days (C) 12 days (D) 18 days
View Solution6 men and 8 women can finish construction of a road in 10 days, 26 men and 48 women can finish this in 2 days. If 15 men and 20 women are appointed for completing this task, then how many days do they need?
View Solution3 men or 4 women can do a piece of work in 43 days. In how many days 7 men & 5 women can do the same work ?
View SolutionIn how many days can 4 women complete a work?
I. 4 men and 4 women can complete the same work in 12 days.
II. 10 women can complete the same work in 16 daysView Solution