"SANJAY Book Depot" can print one lakhs books in 8 hours. "DEVINDER & Sons" can print the same number of books in 10 hours while "HARISH & Sons" can print the same in 12 hours. All of them started printing at 0900 hrs. "SANJAY" is stopped at 1100 hrs and the remanining two machines complete the remaining leftover work. Approximately at what time will the printing of one lakhs books be completed?
1500 hrs
1400 hrs
1400 hrs
1200 hrs
The correct Answer is:C
To solve the problem step by step, we need to calculate the work done by each printing press, the total work completed before Sanjay stops, and then determine how long it will take for Devinder & Sons and Harish & Sons to finish the remaining work.
Step 1: Calculate the work rate of each printing press
1. Sanjay Book Depot:
- Time taken to print 1 lakh books = 8 hours
- Work rate = 1 lakh books / 8 hours = 12,500 books/hour
2. Devinder & Sons:
- Time taken to print 1 lakh books = 10 hours
- Work rate = 1 lakh books / 10 hours = 10,000 books/hour
3. Harish & Sons:
- Time taken to print 1 lakh books = 12 hours
- Work rate = 1 lakh books / 12 hours = 8,333 books/hour
Step 2: Calculate the total work done by all three printing presses in 2 hours
- Work done in 1 hour by all three presses:
- Total work rate = 12,500 + 10,000 + 8,333 = 30,833 books/hour
- Work done in 2 hours:
- Total work done = 30,833 books/hour * 2 hours = 61,666 books
Step 3: Calculate the remaining work after 2 hours
- Total work = 1 lakh books
- Remaining work = Total work - Work done
- Remaining work = 1,00,000 - 61,666 = 38,334 books
Step 4: Calculate the combined work rate of Devinder & Sons and Harish & Sons
- Combined work rate of Devinder & Sons and Harish & Sons:
- Total work rate = 10,000 + 8,333 = 18,333 books/hour
Step 5: Calculate the time taken to complete the remaining work
- Time taken to finish remaining work:
- Time = Remaining work / Combined work rate
- Time = 38,334 books / 18,333 books/hour ≈ 2.09 hours
Step 6: Calculate the completion time
- Sanjay stops at 11:00 hours, and it takes approximately 2.09 hours to finish the remaining work.
- Completion time = 11:00 hours + 2.09 hours ≈ 13:05 hours (or approximately 1:05 PM)
Final Answer
The printing of one lakh books will be completed approximately at 1:05 PM.
---
1. Sanjay Book Depot:
- Time taken to print 1 lakh books = 8 hours
- Work rate = 1 lakh books / 8 hours = 12,500 books/hour
- Time taken to print 1 lakh books = 10 hours
- Work rate = 1 lakh books / 10 hours = 10,000 books/hour
- Time taken to print 1 lakh books = 12 hours
- Work rate = 1 lakh books / 12 hours = 8,333 books/hour
- Work done in 1 hour by all three presses:
- Total work rate = 12,500 + 10,000 + 8,333 = 30,833 books/hour
- Total work done = 30,833 books/hour * 2 hours = 61,666 books
- Total work = 1 lakh books
- Remaining work = Total work - Work done
- Remaining work = 1,00,000 - 61,666 = 38,334 books
- Combined work rate of Devinder & Sons and Harish & Sons:
- Total work rate = 10,000 + 8,333 = 18,333 books/hour
- Time taken to finish remaining work:
- Time = Remaining work / Combined work rate
- Time = 38,334 books / 18,333 books/hour ≈ 2.09 hours
- Sanjay stops at 11:00 hours, and it takes approximately 2.09 hours to finish the remaining work.
- Completion time = 11:00 hours + 2.09 hours ≈ 13:05 hours (or approximately 1:05 PM)
The printing of one lakh books will be completed approximately at 1:05 PM.
Topper's Solved these Questions
Similar Questions
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished? a. 11:30 a.m. b. 12 noon c. 12:30 p.m. d. 1 p.m.
View SolutionA can do a piece of work in 4 hours. (B + C) can do the same work in 3 hours. (A + C) can do the same work in 2 hours. In how many hours will B do this work alone ?
View Solution
Knowledge Check
Machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print the same number of books in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished ?
A11:30 AMB12 noonC12 :30 p.m.D1 p.m.Machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print the same number of books in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished ?
A12⋅00 NoonB12⋅30 PmC1⋅00 PMD11⋅30 AML alone can complete a work in 200 hours. M alone can complete the same work in 150 hours. L, M and N together can complete the same work in 60 hours. In how many hours can N alone complete the work?
A200B240C180D120
A can do a work in 8 hours & B can do the same work in 12 hours. If they workalternatively (one hour A works and one hour B works) and A starts the work at 9 AM, then the work will be completed at __O'clock.
View SolutionA man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone he can do the work in
View SolutionA man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone he can do the work in
View SolutionVijay can do a work in 8 hours. Vijay and Puneet together can do the same work in 6 hours. Puneet and Sachin together can do the same work in 4 hours. Sachin alone can complete the same work in how many hours ?
View SolutionA can do a piece of work in 2 hours, B can do thrice the work in 8 hours and C can do the same work as A in 8 hours. If all of them work together, how long it would take them to complete the work :
View Solution