Pruthi and Shakil can complete a work in 20 days and 12 days respectively. Pruthi alone started the work and Shakil joined him after 4 days till the completion of the work. How long dd the work last?

A

5 days

B

10 days

C

14 days

D

22 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first determine the work done by Pruthi and Shakil individually, then calculate the work done during the time they worked together.

Step 1: Determine the work rates of Pruthi and Shakil
- Pruthi can complete the work in 20 days, so his work rate is:
Pruthi's work rate=120 work/day

- Shakil can complete the work in 12 days, so his work rate is:
Shakil's work rate=112 work/day

Step 2: Calculate the total work in terms of a common unit
To make calculations easier, we can assume the total work is 60 units (the least common multiple of 20 and 12).

- Therefore, Pruthi's efficiency in terms of work units is:
Pruthi's efficiency=6020=3 units/day

- And Shakil's efficiency is:
Shakil's efficiency=6012=5 units/day

Step 3: Calculate the work done by Pruthi in the first 4 days
- In the first 4 days, Pruthi works alone:
Work done by Pruthi in 4 days=3 units/day×4 days=12 units

Step 4: Calculate the remaining work
- The total work is 60 units, and Pruthi has completed 12 units. Therefore, the remaining work is:
Remaining work=6012=48 units

Step 5: Calculate the combined work rate of Pruthi and Shakil
- When Shakil joins Pruthi, their combined work rate is:
Combined work rate=3+5=8 units/day

Step 6: Calculate the time taken to complete the remaining work
- To find the time (D) taken to complete the remaining 48 units of work together:
D=Remaining workCombined work rate=48 units8 units/day=6 days

Step 7: Calculate the total time taken to complete the work
- The total time taken to complete the work is the time Pruthi worked alone plus the time they worked together:
Total time=4 days+6 days=10 days

Thus, the total duration of the work is 10 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • X and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?

    A6 days
    B10 days
    C30 days
    D36 days