Pruthi and Shakil can complete a work in 20 days and 12 days respectively. Pruthi alone started the work and Shakil joined him after 4 days till the completion of the work. How long dd the work last?
5 days
10 days
14 days
22 days
The correct Answer is:B
To solve the problem step by step, we will first determine the work done by Pruthi and Shakil individually, then calculate the work done during the time they worked together.
Step 1: Determine the work rates of Pruthi and Shakil
- Pruthi can complete the work in 20 days, so his work rate is:
Pruthi's work rate=120 work/day
- Shakil can complete the work in 12 days, so his work rate is:
Shakil's work rate=112 work/day
Step 2: Calculate the total work in terms of a common unit
To make calculations easier, we can assume the total work is 60 units (the least common multiple of 20 and 12).
- Therefore, Pruthi's efficiency in terms of work units is:
Pruthi's efficiency=6020=3 units/day
- And Shakil's efficiency is:
Shakil's efficiency=6012=5 units/day
Step 3: Calculate the work done by Pruthi in the first 4 days
- In the first 4 days, Pruthi works alone:
Work done by Pruthi in 4 days=3 units/day×4 days=12 units
Step 4: Calculate the remaining work
- The total work is 60 units, and Pruthi has completed 12 units. Therefore, the remaining work is:
Remaining work=60−12=48 units
Step 5: Calculate the combined work rate of Pruthi and Shakil
- When Shakil joins Pruthi, their combined work rate is:
Combined work rate=3+5=8 units/day
Step 6: Calculate the time taken to complete the remaining work
- To find the time (D) taken to complete the remaining 48 units of work together:
D=Remaining workCombined work rate=48 units8 units/day=6 days
Step 7: Calculate the total time taken to complete the work
- The total time taken to complete the work is the time Pruthi worked alone plus the time they worked together:
Total time=4 days+6 days=10 days
Thus, the total duration of the work is 10 days.
---
- Pruthi can complete the work in 20 days, so his work rate is:
Pruthi's work rate=120 work/day
Shakil's work rate=112 work/day
To make calculations easier, we can assume the total work is 60 units (the least common multiple of 20 and 12).
Pruthi's efficiency=6020=3 units/day
- And Shakil's efficiency is:
Shakil's efficiency=6012=5 units/day
- In the first 4 days, Pruthi works alone:
Work done by Pruthi in 4 days=3 units/day×4 days=12 units
- The total work is 60 units, and Pruthi has completed 12 units. Therefore, the remaining work is:
Remaining work=60−12=48 units
- When Shakil joins Pruthi, their combined work rate is:
Combined work rate=3+5=8 units/day
- To find the time (D) taken to complete the remaining 48 units of work together:
D=Remaining workCombined work rate=48 units8 units/day=6 days
- The total time taken to complete the work is the time Pruthi worked alone plus the time they worked together:
Total time=4 days+6 days=10 days
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View Solution
Knowledge Check
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 daysA and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 daysX and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?
A6 daysB10 daysC30 daysD36 days
A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View SolutionA and B alone can complete work in 9 days and 18 days respectively. They worked together, however 3 days before the completion of the work A left. In how many days was the work completed ?
View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?
View SolutionMahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all the work would be completed in…
View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution