Doubtnut Promotions Sticky

A man do a work in 12 days working 8 h per day. If he does 6 h per day, what would be the number of days taken by him?

A

12 days

B

14 days

C

16 days

D

18 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for A man do a work in 12 days working 8 h per day. If he does 6 h per day, what would be the number of days taken by him? by Maths experts to help you in doubts & scoring excellent marks in Class 6 exams.

Updated on:21/07/2023

Similar Practice Problems

  • Question 1 - Select One

    40 men can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 men will take to build a similar wall 300 m long, working 6 h per day

    A32
    B18
    C36
    D9
  • Question 1 - Select One

    18 men can do 3 units of work in 10 days by doing 8 hours in a day. Then find the required number of days taken by 10 men to complete 5 units of work if they work 6 hours in a day

    A32 days
    B45 days
    C36 days
    D40 days
  • Question 1 - Select One

    A man completes a work in 10 days by doing 5 hours per day. By doing 7 hours per day, he can complete this work in -

    A12 days
    B10 days
    C7 days
    DNone of these
  • Question 1 - Select One

    A certain number of people can complete can complete a piece of work in 12 days working 5 hours a day. If thenumber of men is decreased by half, how many hours a day should they work, so that the work is to be completed in 15 days ?

    A10
    B9
    C8
    D6
  • Question 1 - Select One

    A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.

    A5511
    B4511
    C6411
    D6511
  • Question 1 - Select One

    A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is

    A3
    B5
    C10
    D121

Similar Questions