50 persons can do a work in 12 days, working 6 h per day. 60 persons can do the same work in 8 days, working x h per days.The value of x is
15
712
523
5
To solve the problem, we will follow these steps:
Step 1: Calculate the total work done in hours by the first group of workers.
Given that 50 persons can complete the work in 12 days, working 6 hours per day, we can calculate the total work in hours.
Total Work=Number of Persons×Days×Hours per Day
Total Work=50×12×6
Step 2: Calculate the total work done by the first group.
Now, we compute the total work:
50×12=600(total days worked)
600×6=3600(total hours worked)
So, the total work is 3600 hours.
Step 3: Set up the equation for the second group of workers.
Now, we know that 60 persons can do the same work in 8 days, working x hours per day. We can set up the equation for the total work done by this group:
Total Work=60×8×x
Step 4: Equate the total work from both groups.
Since both groups are doing the same amount of work, we can equate the two expressions for total work:
3600=60×8×x
Step 5: Solve for x.
Now, we can simplify the equation to find x:
3600=480x(since 60×8=480)
x=3600480
x=7.5
Step 6: Convert x to a mixed number.
The value of x can be expressed as:
x=712 hours
Thus, the value of x is 712 hours.
---
Given that 50 persons can complete the work in 12 days, working 6 hours per day, we can calculate the total work in hours.
Total Work=50×12×6
Now, we compute the total work:
600×6=3600(total hours worked)
Now, we know that 60 persons can do the same work in 8 days, working x hours per day. We can set up the equation for the total work done by this group:
Since both groups are doing the same amount of work, we can equate the two expressions for total work:
Now, we can simplify the equation to find x:
x=3600480
x=7.5
The value of x can be expressed as:
Similar Questions
If M1 men can do W1 work in D1 days working H1 hours per day and M2 men can do W2 work in D2 days working H2 hours per day then
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
- Question 1 - Select One
A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.
A5511B4511C6411D6511 - Question 2 - Select One
A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?
A4B5411C6411D4411 - Question 3 - Select One
A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?
A4B5411C6411D4411
If six men can do a piece of work in 6 days, then 3 men can do same work in 10 days (b) 12 days (c) 15 days (d) 18 days
View SolutionIf 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :
View SolutionIf 3 persons can do a piece of work in 4 days, then 4 persons can do it in …… days.
View SolutionIf x men can do a piece of work in y days, in how many days will x men do the same work ?
View SolutionWorking 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in
View Solution