Doubtnut Promotions Sticky

A can do a piece of work in 8 days which B can destroy in 3 days. A has worked for 6 days, during the last 2 days of which B has been destroying: how many days must A now work alone to complete the Work ?

A

7 days

B

713 days

C

723 days

D

8 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we can follow these calculations:

Step 1: Determine the total work done by A and B
A can complete the work in 8 days, which means A's work rate is:
Work rate of A=18 work per day

B can destroy the work in 3 days, which means B's work rate is:
Work rate of B=13 work per day

Step 2: Find the least common multiple (LCM) of the days
To find a common time frame for A and B, we need to calculate the LCM of 8 and 3:
LCM(8,3)=24 days

Step 3: Calculate total work in terms of LCM
In 24 days:
- A would complete:
Total work by A=24×18=3 units of work
- B would destroy:
Total work by B=24×(13)=8 units of work

Step 4: Calculate the net work done in 24 days
The net work done when both A and B work together for 24 days is:
Net work=38=5 units of work
This means that in 24 days, A and B together can effectively complete:
Effective work done=3+8=11 units of work

Step 5: Calculate work done by A in 6 days
A has worked for 6 days. In those 6 days, A has completed:
Work done by A in 6 days=6×18=68=34 units of work

Step 6: Calculate work done by B in the last 2 days
During the last 2 days, B has been destroying work:
Work destroyed by B in 2 days=2×(13)=23 units of work

Step 7: Calculate the total work done after 6 days
Now, we can find the total work done after 6 days:
Total work done=3423
To perform this calculation, we need a common denominator, which is 12:
34=912,23=812
Thus,
Total work done=912812=112 units of work

Step 8: Calculate remaining work
The total work is 1 unit (since A can complete it in 8 days, and B can destroy it in 3 days). Therefore, the remaining work is:
Remaining work=1112=1112 units of work

Step 9: Calculate how many days A needs to work alone
A's work rate is 18 units per day. To find out how many days A needs to work alone to complete the remaining work:
Days needed=Remaining workWork rate of A=111218=1112×8=8812=223 days
This can be converted to:
223 days=713 days

Final Answer
A must work alone for 713 days to complete the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 8 days which B can destroy in 3 days. A has worked for 6 days, during the last 2 days of which B has been destroying: how many days must A now work alone to complete the Work ?

    A7 days
    B713 days
    C723 days
    D8 days
  • Question 2 - Select One

    A can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?

    A10.5
    B8
    C283
    D9
  • Question 3 - Select One

    A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

    A10.5
    B8
    C8.4
    D9