A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
A) 20
B) 30
C) 18
D) 24
The correct Answer is:A
To solve the problem step by step, we will first determine the work done by A, B, and C individually, then calculate how much work they complete together in 4 days, and finally find out how long A and B will take to finish the remaining work.
Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the job in 50 days, so the work done by A in one day is:
Work by A=150 of the job
- B can complete the job in 75 days, so the work done by B in one day is:
Work by B=175 of the job
- C can complete the job in 20 days, so the work done by C in one day is:
Work by C=120 of the job
Step 2: Find the total work done by A, B, and C in one day.
To find the total work done by A, B, and C together in one day, we sum their individual contributions:
Total work in one day=150+175+120
To add these fractions, we need a common denominator. The least common multiple (LCM) of 50, 75, and 20 is 300. Now we convert each fraction:
- For A:
150=6300
- For B:
175=4300
- For C:
120=15300
Now, adding these together:
Total work in one day=6+4+15300=25300=112
Step 3: Calculate the total work done by A, B, and C in 4 days.
If they work together for 4 days, the total work done is:
Work done in 4 days=4×112=412=13
Step 4: Calculate the remaining work.
The total work is considered as 1 (the whole job). Therefore, the remaining work after 4 days is:
Remaining work=1−13=23
Step 5: Calculate the work done by A and B together in one day.
Now, we need to find out how much work A and B can do together in one day:
Work by A and B in one day=150+175
Using the common denominator of 150:
- For A:
150=3150
- For B:
175=2150
Adding these:
Total work by A and B in one day=3+2150=5150=130
Step 6: Calculate the number of days A and B will take to finish the remaining work.
Now we need to find how many days it will take A and B to complete the remaining work of 23:
Days required=Remaining workWork done by A and B in one day=23130=23×30=20
Final Answer:
A and B will take 20 days to finish the remaining work.
---
Work by A=150 of the job
Work by B=175 of the job
Work by C=120 of the job
Total work in one day=150+175+120
150=6300
175=4300
120=15300
Total work in one day=6+4+15300=25300=112
Work done in 4 days=4×112=412=13
Remaining work=1−13=23
Work by A and B in one day=150+175
- For A:
150=3150
175=2150
Total work by A and B in one day=3+2150=5150=130
Days required=Remaining workWork done by A and B in one day=23130=23×30=20
A and B will take 20 days to finish the remaining work.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-III31videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-IV32videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF25videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
A,B andC can do a job working alone in 12, 16 and 24 days, respectively.In how many days, they can do the job, if they worked together?
View SolutionA, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?
View Solution
Knowledge Check
- Question 1 - Select One
If A, B and C can do a job working alone in 12, 18 and 36 days respectively. They all work together for 2 day, then B quits. How many days will A and C take to finish rest of the job?
A9B6C3D4 - Question 2 - Select One
A, B and C can do a job working alone in 6, 9 and 18 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to complete the remainder of the job?
A9B6C12D10 - Question 3 - Select One
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b. 24 days c. 30 days d. 36 days
A18 daysB24 daysC30 daysD36 days
A and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View SolutionA can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?
View SolutionA and B together can do a work in 12 days. A alone can do this in 20 days. If B works half a day then in how many days A and B together can complete the work?
View SolutionA completes 23 of a certain job in 6 days. B can complete 13 of the same job in 8 days and C can complete 34 of the work in 12 days. All of them work together for 4 days and then A and C quit. How long will it take for B to complete the remaining work alone?
View Solution