Doubtnut Promotions Sticky

A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?

A

A) 20

B

B) 30

C

C) 18

D

D) 24

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the work done by A, B, and C individually, then calculate how much work they complete together in 4 days, and finally find out how long A and B will take to finish the remaining work.

Step 1: Calculate the work done by A, B, and C in one day.

- A can complete the job in 50 days, so the work done by A in one day is:
Work by A=150 of the job

- B can complete the job in 75 days, so the work done by B in one day is:
Work by B=175 of the job

- C can complete the job in 20 days, so the work done by C in one day is:
Work by C=120 of the job

Step 2: Find the total work done by A, B, and C in one day.

To find the total work done by A, B, and C together in one day, we sum their individual contributions:
Total work in one day=150+175+120

To add these fractions, we need a common denominator. The least common multiple (LCM) of 50, 75, and 20 is 300. Now we convert each fraction:

- For A:
150=6300

- For B:
175=4300

- For C:
120=15300

Now, adding these together:
Total work in one day=6+4+15300=25300=112

Step 3: Calculate the total work done by A, B, and C in 4 days.

If they work together for 4 days, the total work done is:
Work done in 4 days=4×112=412=13

Step 4: Calculate the remaining work.

The total work is considered as 1 (the whole job). Therefore, the remaining work after 4 days is:
Remaining work=113=23

Step 5: Calculate the work done by A and B together in one day.

Now, we need to find out how much work A and B can do together in one day:
Work by A and B in one day=150+175

Using the common denominator of 150:
- For A:
150=3150

- For B:
175=2150

Adding these:
Total work by A and B in one day=3+2150=5150=130

Step 6: Calculate the number of days A and B will take to finish the remaining work.

Now we need to find how many days it will take A and B to complete the remaining work of 23:
Days required=Remaining workWork done by A and B in one day=23130=23×30=20

Final Answer:
A and B will take 20 days to finish the remaining work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If A, B and C can do a job working alone in 12, 18 and 36 days respectively. They all work together for 2 day, then B quits. How many days will A and C take to finish rest of the job?

    A9
    B6
    C3
    D4
  • Question 2 - Select One

    A, B and C can do a job working alone in 6, 9 and 18 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to complete the remainder of the job?

    A9
    B6
    C12
    D10
  • Question 3 - Select One

    A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b.  24 days c. 30 days d. 36 days

    A18 days
    B24 days
    C30 days
    D36 days