A can complete a work in 10 days and B can complete it in 15 days. If A starts the work and 5 days later B also joins him, then in how many days the work will be finished?
6 days
7 days
10 days
8 days
The correct Answer is:C
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work rates of A and B
- A can complete the work in 10 days. Therefore, A's work rate is:
Rate of A=110 work/day
- B can complete the work in 15 days. Therefore, B's work rate is:
Rate of B=115 work/day
Step 2: Calculate the amount of work done by A in the first 5 days
- In 5 days, A will complete:
Work done by A in 5 days=5×110=510=12 of the work
Step 3: Determine the remaining work after 5 days
- Since A completed half of the work, the remaining work is:
Remaining work=1−12=12 of the work
Step 4: Calculate the combined work rate of A and B
- When B joins A, their combined work rate will be:
Combined Rate=110+115
- To add these fractions, we find a common denominator, which is 30:
Combined Rate=330+230=530=16 work/day
Step 5: Determine how long it takes for A and B to finish the remaining work
- The remaining work is 12. To find the time taken to complete this work at their combined rate:
Time=Remaining WorkCombined Rate=1216=12×6=3 days
Step 6: Calculate the total time taken to complete the work
- The total time taken to complete the work is the time A worked alone plus the time A and B worked together:
Total Time=5 days (A alone)+3 days (A and B together)=8 days
Final Answer
The work will be finished in 8 days.
---
- A can complete the work in 10 days. Therefore, A's work rate is:
Rate of A=110 work/day
- B can complete the work in 15 days. Therefore, B's work rate is:
Rate of B=115 work/day
- In 5 days, A will complete:
Work done by A in 5 days=5×110=510=12 of the work
- Since A completed half of the work, the remaining work is:
Remaining work=1−12=12 of the work
- When B joins A, their combined work rate will be:
Combined Rate=110+115
- To add these fractions, we find a common denominator, which is 30:
Combined Rate=330+230=530=16 work/day
- The remaining work is 12. To find the time taken to complete this work at their combined rate:
Time=Remaining WorkCombined Rate=1216=12×6=3 days
- The total time taken to complete the work is the time A worked alone plus the time A and B worked together:
Total Time=5 days (A alone)+3 days (A and B together)=8 days
The work will be finished in 8 days.
Topper's Solved these Questions
Similar Questions
A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View SolutionA and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days
View Solution
Knowledge Check
A can do a work in 6 days, B can do it in 8 days and C can complete it in 12 days. If A starts the work and they work in alternatively, then in how many days, the work will be completed?
A635B723C525D623A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?
A10B8C12D9A and B together can do a work in 12 days. A alone can do this in 20 days. If B works half a day then in how many days A and B together can complete the work?
A10 daysB20 daysC11 daysD15 days
A can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View SolutionMahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all the work would be completed in…
View SolutionA can finish a work in 10 days if he works 4 hours per day. B can complete it in 15 days if he works 5 hours per day. If they work 10 hours per day, then in how many days the work will be finished?
View SolutionA can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View SolutionA can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View Solution