A can complete a work in 10 days and B can complete it in 15 days. If A starts the work and 5 days later B also joins him, then in how many days the work will be finished?

A

6 days

B

7 days

C

10 days

D

8 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work rates of A and B
- A can complete the work in 10 days. Therefore, A's work rate is:
Rate of A=110 work/day
- B can complete the work in 15 days. Therefore, B's work rate is:
Rate of B=115 work/day

Step 2: Calculate the amount of work done by A in the first 5 days
- In 5 days, A will complete:
Work done by A in 5 days=5×110=510=12 of the work

Step 3: Determine the remaining work after 5 days
- Since A completed half of the work, the remaining work is:
Remaining work=112=12 of the work

Step 4: Calculate the combined work rate of A and B
- When B joins A, their combined work rate will be:
Combined Rate=110+115
- To add these fractions, we find a common denominator, which is 30:
Combined Rate=330+230=530=16 work/day

Step 5: Determine how long it takes for A and B to finish the remaining work
- The remaining work is 12. To find the time taken to complete this work at their combined rate:
Time=Remaining WorkCombined Rate=1216=12×6=3 days

Step 6: Calculate the total time taken to complete the work
- The total time taken to complete the work is the time A worked alone plus the time A and B worked together:
Total Time=5 days (A alone)+3 days (A and B together)=8 days

Final Answer
The work will be finished in 8 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a work in 6 days, B can do it in 8 days and C can complete it in 12 days. If A starts the work and they work in alternatively, then in how many days, the work will be completed?

    A635
    B723
    C525
    D623
  • A can do a work in 10 days and B can do the same in 20 days. If they start the work together and A leaves that work 5 days before completion, in how many days the work will be finished?

    A10
    B8
    C12
    D9
  • A and B together can do a work in 12 days. A alone can do this in 20 days. If B works half a day then in how many days A and B together can complete the work?

    A10 days
    B20 days
    C11 days
    D15 days