Doubtnut Promotions Sticky

10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?

A

6

B

6 1 3

C

6 2 3

D

7 2 3

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work done by the men and women individually, and then combine their efforts to find out how long it will take them to complete the work together.

Step 1: Determine the total work in terms of units.
Given that 10 men can complete the work in 15 days, we can calculate the total work in units.

- Total work = Number of men × Days × Work done per day by each man.
- Let's assume the total work is 60 units (as derived from the LCM approach in the video).

Step 2: Calculate the work done by 10 men in one day.
- Work done by 10 men in 15 days = 60 units.
- Therefore, work done by 10 men in 1 day = Total work / Days = 60 units / 15 days = 4 units.

Step 3: Calculate the work done by 15 women in one day.
Given that 15 women can complete the same work in 12 days:

- Work done by 15 women in 12 days = 60 units.
- Therefore, work done by 15 women in 1 day = Total work / Days = 60 units / 12 days = 5 units.

Step 4: Calculate the combined work done by 10 men and 15 women in one day.
- Combined work done in one day = Work done by 10 men + Work done by 15 women = 4 units + 5 units = 9 units.

Step 5: Calculate the total number of days required to complete the work together.
- Total work = 60 units.
- Work done in one day = 9 units.
- Therefore, number of days required = Total work / Work done in one day = 60 units / 9 units = 6.67 days, which can be expressed as 6 complete 2/3 days.

Final Answer:
The work will be completed in 6 complete 2/3 days.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32
  • Question 2 - Select One

    12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

    A16
    B12
    C18
    D10
  • Question 3 - Select One

    3 men can do a piece of work in 6 days. 5 women can do the same work in 18 days. If 4 men and 10 women work together, then how long will it take to finish the work?

    A3 days
    B5 days
    C2 days
    D4 days