A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of wall?
(a)1313 days
(b)713 days
(c)613 days
(d)7 days
1313 days
713 days
613 days
7 days
The correct Answer is:B
To solve the problem step by step, we will follow the given information and perform calculations accordingly.
Step 1: Determine the work done by A and B
- A can build the wall in 8 days. Therefore, the work done by A in one day is:
Work done by A in 1 day=18 of the wall
- B can break the wall in 3 days. Therefore, the work done by B in one day is:
Work done by B in 1 day=−13 of the wall
(Note: B's work is negative because he is breaking the wall.)
Step 2: Calculate the total work in terms of units
To make calculations easier, we can consider the total work to build the wall as 24 units (the least common multiple of 8 and 3).
- Work done by A in one day:
A's work in one day=248=3 units
- Work done by B in one day:
B's work in one day=−243=−8 units
Step 3: Calculate the work done by A in the first 4 days
A works alone for 4 days:
Work done by A in 4 days=4×3=12 units
Step 4: Calculate the work done by A and B together for 2 days
When B joins A, they work together for 2 days. The combined work done by A and B in one day is:
Combined work in one day=3−8=−5 units
Thus, in 2 days, the work done is:
Work done by A and B in 2 days=2×(−5)=−10 units
Step 5: Calculate the total work done so far
Now, we can calculate the total work done:
Total work done=Work done by A in 4 days+Work done by A and B in 2 days
Total work done=12+(−10)=2 units
Step 6: Calculate the remaining work
The total work required to build the wall is 24 units. Therefore, the remaining work is:
Remaining work=24−2=22 units
Step 7: Calculate the time taken by A to finish the remaining work
Now, we need to find out how many days A will take to complete the remaining 22 units of work:
Days taken by A=Remaining workWork done by A in one day=223
Calculating this gives:
223=713 days
Final Answer
Thus, A will take 713 days to build the remaining part of the wall.
- A can build the wall in 8 days. Therefore, the work done by A in one day is:
Work done by A in 1 day=18 of the wall
- B can break the wall in 3 days. Therefore, the work done by B in one day is:
Work done by B in 1 day=−13 of the wall
(Note: B's work is negative because he is breaking the wall.)
To make calculations easier, we can consider the total work to build the wall as 24 units (the least common multiple of 8 and 3).
- Work done by A in one day:
A's work in one day=248=3 units
- Work done by B in one day:
B's work in one day=−243=−8 units
A works alone for 4 days:
Work done by A in 4 days=4×3=12 units
When B joins A, they work together for 2 days. The combined work done by A and B in one day is:
Combined work in one day=3−8=−5 units
Thus, in 2 days, the work done is:
Work done by A and B in 2 days=2×(−5)=−10 units
Now, we can calculate the total work done:
Total work done=Work done by A in 4 days+Work done by A and B in 2 days
Total work done=12+(−10)=2 units
The total work required to build the wall is 24 units. Therefore, the remaining work is:
Remaining work=24−2=22 units
Now, we need to find out how many days A will take to complete the remaining 22 units of work:
Days taken by A=Remaining workWork done by A in one day=223
Calculating this gives:
223=713 days
Thus, A will take 713 days to build the remaining part of the wall.
Topper's Solved these Questions
- BOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)37videos
TIME AND WORK
- BOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)27videos
TIME AND WORK
- BOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself15videos
TIME AND WORK
- BOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself15videos
SET THEORY
- BOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself15videos
TIME, SPEED AND DISTANCE
Similar Questions
Knowledge Check
- Question 1 - Select One
A can build up a structure in 8 days and B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only . In how many days will A alone builed up the remaining part of the structure ?
A10 daysB9 daysC713 daysD13 days - Question 2 - Select One
A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?
A12B68C72D90 - Question 3 - Select One
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62
A work for 2 days, then B complete the remaining work in 9 days. If A work for 3 days, then B complete the remaining work in 6 days. In how many days will A and B do this work alone ?
View SolutionA can do a work in 12 days when he had worked for 3 days B joined him if they complete the work in 3 more days in how many days can B alone finish the work?
View SolutionA can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?
View SolutionA can do one-third of a work in 15 days. B can do 75% of the same work in 18 days and C can do the same work in 36 days. B and C work together for 8 days. In how many days will A alone complete the remaining work?
View SolutionA can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
View Solution