A and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?
6 days
4 days
5 days
7 days
The correct Answer is:C
To solve the problem, we will follow these steps:
Step 1: Determine the work done by A and B in one day.
- A can complete the job in 16 days, so A's work rate is 116 of the job per day.
- B can complete the job in 12 days, so B's work rate is 112 of the job per day.
Step 2: Find the total work in terms of a common unit.
- The least common multiple (LCM) of 16 and 12 is 48. Therefore, we can consider the total work to be 48 units.
- A's work rate: 4816=3 units per day.
- B's work rate: 4812=4 units per day.
Step 3: Calculate the work done by A and B together.
- When A joins B, their combined work rate is 3+4=7 units per day.
Step 4: Determine the time they worked together.
- B started the work alone 4 days before A joined. Let’s denote the total time taken to complete the work as T days.
- Therefore, A and B worked together for 4 days, and B worked alone for T−4 days.
Step 5: Calculate the total work done.
- The work done by B alone in T−4 days is 4(T−4) units.
- The work done by A and B together in 4 days is 7×4=28 units.
- The total work done can be expressed as:
4(T−4)+28=48
Step 6: Solve for T.
- Expanding the equation:
4T−16+28=48
4T+12=48
4T=48−12
4T=36
T=9
Step 7: Calculate how many days B worked alone.
- Since T=9, the number of days B worked alone is:
T−4=9−4=5 days
Conclusion:
B has worked alone for 5 days.
---
- A can complete the job in 16 days, so A's work rate is 116 of the job per day.
- B can complete the job in 12 days, so B's work rate is 112 of the job per day.
- The least common multiple (LCM) of 16 and 12 is 48. Therefore, we can consider the total work to be 48 units.
- A's work rate: 4816=3 units per day.
- B's work rate: 4812=4 units per day.
- When A joins B, their combined work rate is 3+4=7 units per day.
- B started the work alone 4 days before A joined. Let’s denote the total time taken to complete the work as T days.
- Therefore, A and B worked together for 4 days, and B worked alone for T−4 days.
- The work done by B alone in T−4 days is 4(T−4) units.
- The work done by A and B together in 4 days is 7×4=28 units.
- The total work done can be expressed as:
4(T−4)+28=48
- Expanding the equation:
4T−16+28=48
4T+12=48
4T=48−12
4T=36
T=9
- Since T=9, the number of days B worked alone is:
T−4=9−4=5 days
B has worked alone for 5 days.
Topper's Solved these Questions
- BOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)37videos
TIME AND WORK
- BOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)27videos
TIME AND WORK
- BOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself15videos
TIME AND WORK
- BOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself15videos
SET THEORY
- BOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself15videos
TIME, SPEED AND DISTANCE
Similar Questions
A can do a work in 10 days and that of B in 15 days . B starts the work alone but after 3 days he left the work & A joined the work . In how many days will the total work be finished ?
View SolutionA, b and C can alone complete a work in 10, 12 and 15 days
respectively. A and C started the work and after working for
4 days, A left and B joined. In how many days the total work
was completed ?View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 days - Question 2 - Select One
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 days - Question 3 - Select One
A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
A2 daysB3 daysC1 dayDNone of these
A, B and C can do a job working alone in 6, 9 and 18 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to complete the remainder of the job?
View SolutionA and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
View SolutionA, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
View SolutionA, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?
View SolutionA, B and C can do job in 9, 12 and 36 days respectively if they worked alone. A leaves after they have worked together for 3 days. In how many days can B and C do the rest of the job?
View Solution