Three diggers dug a ditch of 324 m deep in six days working simultaneously. During one shift, the third digger digs as many metres more than the second as the second digs more than the first. The third digger’s work in 10 days is equal to the first digger’s work in 14 days. How many metres does the first digger dig per shift?
15 m
18 m
21 m
27 m
The correct Answer is:A
To solve the problem step by step, we will break it down into manageable parts.
Step 1: Understand the Problem
We have three diggers (let's call them A, B, and C) who together dig a ditch of 324 meters deep in 6 days. We need to find out how many meters the first digger (A) digs per shift.
Step 2: Calculate Total Work Done Per Day
First, we calculate how much work is done per day by all three diggers combined.
Total work=324 meters
Total days=6 days
Work done per day=324 meters6 days=54 meters/day
Step 3: Set Up the Variables
Let:
- x = work done by Digger A (first digger) in meters per day,
- y = work done by Digger B (second digger) in meters per day,
- z = work done by Digger C (third digger) in meters per day.
According to the problem, we know:
1. x+y+z=54 (total work done by all three diggers per day).
Step 4: Understand the Relationships
From the problem, we have the following relationships:
- The third digger digs as many meters more than the second as the second digs more than the first:
z−y=y−x⟹z=2y−x
- The third digger’s work in 10 days is equal to the first digger’s work in 14 days:
10z=14x⟹z=1410x=1.4x
Step 5: Substitute and Solve
Now we can substitute z in the first equation:
x+y+1.4x=54
2.4x+y=54(1)
Substituting z=2y−x into the equation:
2y−x=1.4x
2y=2.4x⟹y=1.2x(2)
Step 6: Substitute Equation (2) into Equation (1)
Now substitute y=1.2x into equation (1):
2.4x+1.2x=54
3.6x=54
x=543.6=15
Step 7: Conclusion
Thus, the first digger (A) digs 15 meters per shift.
We have three diggers (let's call them A, B, and C) who together dig a ditch of 324 meters deep in 6 days. We need to find out how many meters the first digger (A) digs per shift.
First, we calculate how much work is done per day by all three diggers combined.
Total work=324 meters
Total days=6 days
Work done per day=324 meters6 days=54 meters/day
Let:
- x = work done by Digger A (first digger) in meters per day,
- y = work done by Digger B (second digger) in meters per day,
- z = work done by Digger C (third digger) in meters per day.
1. x+y+z=54 (total work done by all three diggers per day).
From the problem, we have the following relationships:
- The third digger digs as many meters more than the second as the second digs more than the first:
z−y=y−x⟹z=2y−x
10z=14x⟹z=1410x=1.4x
Now we can substitute z in the first equation:
x+y+1.4x=54
2.4x+y=54(1)
2y−x=1.4x
2y=2.4x⟹y=1.2x(2)
Now substitute y=1.2x into equation (1):
2.4x+1.2x=54
3.6x=54
x=543.6=15
Thus, the first digger (A) digs 15 meters per shift.
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)
37 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)
27 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself
15 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
A swimming pool is filled by three pipes with uniform flow. The first two pipes operating simultaneously fill the pool in the same time during which the pool is filled by the third pipe alone. The second pipe fills the pool 5 hours faster than the first pipe and 4 hours slower than the third pipe. The time required by the first pipe is
a. 6 hrs
b. 10 hrs
c. 15 hrs
d. 30 hrs
View Solution20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View Solution
Knowledge Check
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D24Some person can do nay work in 60 days. If 8 person were more, than the work has been finished 10 days before. How many persons were there in starting ?
A40B50C25D30A can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?
A8B3C4D6
The reading style of Sunny is quite unusual. He reads one page on the first day, 2 pages on the second day, 3 pages on the thrid day etc. How many pages Sunny can read in 24 days?
View SolutionA man read 25 th of a book on the first day. He read 13 rd more on second day than he read on the first day. 15 pages were left for the third day. The number of pages in the book is
View SolutionThree typists A, B and C working together 8 hours per a can type 900 pages in 20 days. In a day B types as many pages more than A as C types as many pages more than R number of pages typed by A in 4 hours equal to the number of pages typed by C in 1 hour. How many pages C types in each hour?
View SolutionThree typists A, B and C working together 8 hours per a can type 900 pages in 20 days. In a day B types as many pages more than A as C types as many pages more than R number of pages typed by A in 4 hours equal to the number of pages typed by C in 1 hour. How many pages C types in each hour?
View SolutionB works three times more slowly than A and C together. C can do it twice slowly than A and B. if they work together, the work is completed in 10 days. In how many days they will do it separately?
View Solution