Doubtnut Promotions Sticky

Three diggers dug a ditch of 324 m deep in six days working simultaneously. During one shift, the third digger digs as many metres more than the second as the second digs more than the first. The third digger’s work in 10 days is equal to the first digger’s work in 14 days. How many metres does the first digger dig per shift?

A

15 m

B

18 m

C

21 m

D

27 m

Video Solution
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for Three diggers dug a ditch of 324 m deep in six days working simultaneously. During one shift, the third digger digs as many metres more than the second as the second digs more than the first. The third digger’s work in 10 days is equal to the first digger’s work in 14 days. How many metres does the first digger dig per shift? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?

    A12
    B20
    C18
    D24
  • Question 2 - Select One

    Some person can do nay work in 60 days. If 8 person were more, than the work has been finished 10 days before. How many persons were there in starting ?

    A40
    B50
    C25
    D30
  • Question 3 - Select One

    A can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?

    A8
    B3
    C4
    D6