Three diggers dug a ditch of 324 m deep in six days working simultaneously. During one shift, the third digger digs as many metres more than the second as the second digs more than the first. The third digger’s work in 10 days is equal to the first digger’s work in 14 days. How many metres does the first digger dig per shift?

A

15 m

B

18 m

C

21 m

D

27 m

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will break it down into manageable parts.

Step 1: Understand the Problem
We have three diggers (let's call them A, B, and C) who together dig a ditch of 324 meters deep in 6 days. We need to find out how many meters the first digger (A) digs per shift.

Step 2: Calculate Total Work Done Per Day
First, we calculate how much work is done per day by all three diggers combined.
Total work=324 meters
Total days=6 days
Work done per day=324 meters6 days=54 meters/day

Step 3: Set Up the Variables
Let:
- x = work done by Digger A (first digger) in meters per day,
- y = work done by Digger B (second digger) in meters per day,
- z = work done by Digger C (third digger) in meters per day.

According to the problem, we know:
1. x+y+z=54 (total work done by all three diggers per day).

Step 4: Understand the Relationships
From the problem, we have the following relationships:
- The third digger digs as many meters more than the second as the second digs more than the first:
zy=yxz=2yx

- The third digger’s work in 10 days is equal to the first digger’s work in 14 days:
10z=14xz=1410x=1.4x

Step 5: Substitute and Solve
Now we can substitute z in the first equation:
x+y+1.4x=54
2.4x+y=54(1)

Substituting z=2yx into the equation:
2yx=1.4x
2y=2.4xy=1.2x(2)

Step 6: Substitute Equation (2) into Equation (1)
Now substitute y=1.2x into equation (1):
2.4x+1.2x=54
3.6x=54
x=543.6=15

Step 7: Conclusion
Thus, the first digger (A) digs 15 meters per shift.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • 40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?

    A12
    B20
    C18
    D24
  • Some person can do nay work in 60 days. If 8 person were more, than the work has been finished 10 days before. How many persons were there in starting ?

    A40
    B50
    C25
    D30
  • A can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?

    A8
    B3
    C4
    D6