A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

A

2 days

B

3 days

C

1 day

D

None of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's break it down:

Step 1: Determine the work done by A and B in one day.
- A can complete the job in 15 days. Therefore, the work done by A in one day = 115 of the job.
- B can complete the job in 10 days. Therefore, the work done by B in one day = 110 of the job.

Step 2: Calculate the combined work done by A and B in one day.
- Combined work done by A and B in one day = 115+110.
- To add these fractions, we find a common denominator, which is 30.
- 115=230
- 110=330
- Therefore, combined work = 230+330=530=16 of the job.

Step 3: Determine how much work B does alone in 5 days.
- Since B finishes the remaining work in 5 days, the work done by B in 5 days = 5×110=510=12 of the job.

Step 4: Calculate the total work completed before B finishes the job.
- If B completed 12 of the job in 5 days, then the remaining work before B worked alone was also 12 of the job.

Step 5: Determine how many days A and B worked together to complete half the job.
- Since A and B together can complete 16 of the job in one day, we need to find out how many days (let's call it x) they worked together to complete 12 of the job.
- The equation will be:
x×16=12
- Solving for x:
x=1/21/6=12×61=3

Conclusion:
- A and B worked together for 3 days before A left.

Final Answer:
A left after 3 days.

---

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?

    A5 days
    B10 days
    C11 days
    D6 days
  • A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

    A1425 days
    B9days
    C8days
    D759 days
  • A and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?

    A1425 days
    B9 days
    C8 days
    D359 days