Doubtnut Promotions Sticky

X and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?

A

6 days

B

10 days

C

30 days

D

36 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will calculate how long the work lasted when X and Y worked together.

Step 1: Determine the total work
The total work can be calculated based on the time taken by X and Y to complete the work individually.

- X can complete the work in 20 days.
- Y can complete the work in 12 days.

To find the total work in terms of units, we can take the least common multiple (LCM) of their individual work times.

Total Work (TW) = LCM(20, 12)

Calculating the LCM:
- The prime factorization of 20 is 22×51.
- The prime factorization of 12 is 22×31.

The LCM is found by taking the highest power of each prime:
- LCM = 22×31×51=60

So, the total work is 60 units.

Step 2: Calculate the efficiency of X and Y
Next, we calculate the efficiency (work done per day) of X and Y.

- Efficiency of X = Total Work / Days taken by X = 60/20=3 units per day.
- Efficiency of Y = Total Work / Days taken by Y = 60/12=5 units per day.

Step 3: Calculate the work done by X in the first 4 days
Since X starts the work alone for the first 4 days, we can calculate how much work he completes in that time.

- Work done by X in 4 days = Efficiency of X × Number of days = 3×4=12 units.

Step 4: Calculate the remaining work
Now, we find out how much work is left after X has worked alone for 4 days.

- Remaining work = Total Work - Work done by X = 6012=48 units.

Step 5: Calculate the time taken by X and Y to complete the remaining work
Now that both X and Y are working together, we can calculate how much work they can do together in one day.

- Combined efficiency of X and Y = Efficiency of X + Efficiency of Y = 3+5=8 units per day.

Now, we can find out how many days it will take for them to complete the remaining work.

- Time taken to complete remaining work = Remaining work / Combined efficiency = 48/8=6 days.

Step 6: Calculate the total time of work
Finally, we add the time X worked alone to the time taken by both X and Y to complete the remaining work.

- Total time of work = Time worked by X alone + Time worked by X and Y together = 4+6=10 days.

Thus, the total duration of the work is 10 days.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • Question 2 - Select One

    A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • Question 3 - Select One

    A and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
    A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?

    A12
    B9
    C15
    D17