X and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?
6 days
10 days
30 days
36 days
The correct Answer is:B
To solve the problem step by step, we will calculate how long the work lasted when X and Y worked together.
Step 1: Determine the total work
The total work can be calculated based on the time taken by X and Y to complete the work individually.
- X can complete the work in 20 days.
- Y can complete the work in 12 days.
To find the total work in terms of units, we can take the least common multiple (LCM) of their individual work times.
Total Work (TW) = LCM(20, 12)
Calculating the LCM:
- The prime factorization of 20 is 22×51.
- The prime factorization of 12 is 22×31.
The LCM is found by taking the highest power of each prime:
- LCM = 22×31×51=60
So, the total work is 60 units.
Step 2: Calculate the efficiency of X and Y
Next, we calculate the efficiency (work done per day) of X and Y.
- Efficiency of X = Total Work / Days taken by X = 60/20=3 units per day.
- Efficiency of Y = Total Work / Days taken by Y = 60/12=5 units per day.
Step 3: Calculate the work done by X in the first 4 days
Since X starts the work alone for the first 4 days, we can calculate how much work he completes in that time.
- Work done by X in 4 days = Efficiency of X × Number of days = 3×4=12 units.
Step 4: Calculate the remaining work
Now, we find out how much work is left after X has worked alone for 4 days.
- Remaining work = Total Work - Work done by X = 60−12=48 units.
Step 5: Calculate the time taken by X and Y to complete the remaining work
Now that both X and Y are working together, we can calculate how much work they can do together in one day.
- Combined efficiency of X and Y = Efficiency of X + Efficiency of Y = 3+5=8 units per day.
Now, we can find out how many days it will take for them to complete the remaining work.
- Time taken to complete remaining work = Remaining work / Combined efficiency = 48/8=6 days.
Step 6: Calculate the total time of work
Finally, we add the time X worked alone to the time taken by both X and Y to complete the remaining work.
- Total time of work = Time worked by X alone + Time worked by X and Y together = 4+6=10 days.
Thus, the total duration of the work is 10 days.
---
The total work can be calculated based on the time taken by X and Y to complete the work individually.
- Y can complete the work in 12 days.
- The prime factorization of 20 is 22×51.
- The prime factorization of 12 is 22×31.
- LCM = 22×31×51=60
Next, we calculate the efficiency (work done per day) of X and Y.
- Efficiency of Y = Total Work / Days taken by Y = 60/12=5 units per day.
Since X starts the work alone for the first 4 days, we can calculate how much work he completes in that time.
Now, we find out how much work is left after X has worked alone for 4 days.
Now that both X and Y are working together, we can calculate how much work they can do together in one day.
Finally, we add the time X worked alone to the time taken by both X and Y to complete the remaining work.
Topper's Solved these Questions
Similar Questions
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last? 6 days b. 10 days c. 1 5 days d. 20 days
View SolutionA and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 days - Question 2 - Select One
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?
A10 daysB20 daysC15 daysD6 days - Question 3 - Select One
A and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?A12B9C15D17
X and Y can do a piece of work in 20 days and 30 days respectively. The time they take to complete the work by working together is ……………
View SolutionX and Y can do a piece of work in 20 days and 30 days respectively. The time they take to complete the work by working together is ……………
View SolutionA and B can do a piece of work in 20 days and 25 days. A start the work and they do this work in alternate days. In how many days will this work be completed ?
View SolutionPruthi and Shakil can complete a work in 20 days and 12 days respectively. Pruthi alone started the work and Shakil joined him after 4 days till the completion of the work. How long dd the work last?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View Solution