Doubtnut Promotions Sticky

Ram and Shyam together can do a work in 8days. Both of them began to work. After 3 days Ram fell ill, Shyam completed the remaining work in 15 days. In how many days can Ram complete the whole work?

A

12

B

15

C

17

D

16

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's denote the work done by Ram in one day as R and the work done by Shyam in one day as S.

Step 1: Determine the total work done by Ram and Shyam together.
Since Ram and Shyam together can complete the work in 8 days, their combined work per day is:
R+S=18 (work done in one day)

Step 2: Calculate the work done in the first 3 days.
In the first 3 days, both Ram and Shyam work together. Therefore, the work done in 3 days is:
Work done in 3 days=3×(R+S)=3×18=38

Step 3: Determine the remaining work after 3 days.
The total work is considered as 1 (whole work), so the remaining work after 3 days is:
Remaining work=138=58

Step 4: Calculate the work done by Shyam alone in 15 days.
Shyam completes the remaining work in 15 days. Therefore, Shyam's work per day is:
S=Remaining workTime taken by Shyam=5815=5120=124

Step 5: Substitute Shyam's work into the combined work equation.
Now we know Shyam's work per day (S):
S=124
Substituting this value into the combined work equation:
R+124=18

Step 6: Solve for Ram's work (R).
To find R, rearrange the equation:
R=18124
To subtract these fractions, find a common denominator (which is 24):
R=324124=224=112

Step 7: Calculate the time taken by Ram to complete the whole work.
Now that we know Ram's work per day (R):
R=112
To find out how many days Ram would take to complete the whole work alone, we use:
Time taken by Ram=1R=1112=12 days

Final Answer:
Ram can complete the whole work in 12 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • Question 2 - Select One

    A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

    A38
    B51
    C46
    D62
  • Question 3 - Select One

    A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

    A4813 days
    B3513 days
    C267 days
    D247 days