Ram and Shyam together can do a work in 8days. Both of them began to work. After 3 days Ram fell ill, Shyam completed the remaining work in 15 days. In how many days can Ram complete the whole work?
12
15
17
16
To solve the problem step by step, let's denote the work done by Ram in one day as R and the work done by Shyam in one day as S.
Step 1: Determine the total work done by Ram and Shyam together.
Since Ram and Shyam together can complete the work in 8 days, their combined work per day is:
R+S=18 (work done in one day)
Step 2: Calculate the work done in the first 3 days.
In the first 3 days, both Ram and Shyam work together. Therefore, the work done in 3 days is:
Work done in 3 days=3×(R+S)=3×18=38
Step 3: Determine the remaining work after 3 days.
The total work is considered as 1 (whole work), so the remaining work after 3 days is:
Remaining work=1−38=58
Step 4: Calculate the work done by Shyam alone in 15 days.
Shyam completes the remaining work in 15 days. Therefore, Shyam's work per day is:
S=Remaining workTime taken by Shyam=5815=5120=124
Step 5: Substitute Shyam's work into the combined work equation.
Now we know Shyam's work per day (S):
S=124
Substituting this value into the combined work equation:
R+124=18
Step 6: Solve for Ram's work (R).
To find R, rearrange the equation:
R=18−124
To subtract these fractions, find a common denominator (which is 24):
R=324−124=224=112
Step 7: Calculate the time taken by Ram to complete the whole work.
Now that we know Ram's work per day (R):
R=112
To find out how many days Ram would take to complete the whole work alone, we use:
Time taken by Ram=1R=1112=12 days
Final Answer:
Ram can complete the whole work in 12 days.
---
Since Ram and Shyam together can complete the work in 8 days, their combined work per day is:
R+S=18 (work done in one day)
In the first 3 days, both Ram and Shyam work together. Therefore, the work done in 3 days is:
Work done in 3 days=3×(R+S)=3×18=38
The total work is considered as 1 (whole work), so the remaining work after 3 days is:
Remaining work=1−38=58
Shyam completes the remaining work in 15 days. Therefore, Shyam's work per day is:
S=Remaining workTime taken by Shyam=5815=5120=124
Now we know Shyam's work per day (S):
S=124
Substituting this value into the combined work equation:
R+124=18
To find R, rearrange the equation:
R=18−124
To subtract these fractions, find a common denominator (which is 24):
R=324−124=224=112
Now that we know Ram's work per day (R):
R=112
To find out how many days Ram would take to complete the whole work alone, we use:
Time taken by Ram=1R=1112=12 days
Ram can complete the whole work in 12 days.
Similar Questions
A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?
View SolutionA can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days - Question 2 - Select One
A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
A38B51C46D62 - Question 3 - Select One
A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
A4813 daysB3513 daysC267 daysD247 days
P can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?
View SolutionP can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?
View SolutionSunny can complete a piece of work in 30 days He worked for 6 days and left. Bunny completed the remaining work in 16 days. In how many days can the entire work kbe completed if they worik together?
View SolutionA and B can do a work in 6 days and 8 days respectively. Together they worked for 3 days and left. C complete the remaining work in 2 days. Find in how many days B and C together can complete 3/4th part of the total work.
View SolutionU, V and W together can complete a work in 15 days. U alone can complete the work in 60 days. In how many days V and W together can complete the same work?
View Solution