Tired of the day-long labour, no more work could be done.
I could do no more work
Similar Questions
Shashank started a work and left after 12 days, rest work done by Nitish in 15 days. Had Shashank left work, 2 days before, the rest work could have been done by Nitish in 18 days. If Shashank reduces his efficiency by 20% and Nitish increase his efficiency by 50%. Then in how many day working together they will finish the work?
View SolutionA group of laboures promises to do a plece of work in 10 days, but five of them become absent. If the remaining labourers complete the work in 12 days. Find their original number in the group.
View Solution
Knowledge Check
- Question 1 - Select One
A is more efficient than B and they together can complete a work in 24 days. Had A done 50% of the work and then B, the remaining work, then the work would have been done in 50 days, B alone will complete 40% of the same work in:
A16 daysB24 daysC21 daysD20 days - Question 2 - Select One
'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
A6B10C12D15 - Question 3 - Select One
A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:
A30B40C32D36
'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is
View SolutionA certain number of men complete a work in 45 days. If there were 5 men more, the work could be fin- ished in 9 days less How many men were originally there?
View SolutionA certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished 11 days Earlier. How many persons were there when the work started?
View Solution40 men could have finished the whole project in 28 days but due to the inclusion of a few more men, work got done in 3/4 of the time. Find the ratio of number of new men to number of old men.
View Solutiona certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?
View Solution