Doubtnut Promotions Sticky

Tired of the day-long labour, no more work could be done.

Text Solution
Verified by Experts

I could do no more work

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is more efficient than B and they together can complete a work in 24 days. Had A done 50% of the work and then B, the remaining work, then the work would have been done in 50 days, B alone will complete 40% of the same work in:

    A16 days
    B24 days
    C21 days
    D20 days
  • Question 2 - Select One

    'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is

    A6
    B10
    C12
    D15
  • Question 3 - Select One

    A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:

    A30
    B40
    C32
    D36