Shashank started a work and left after 12 days, rest work done by Nitish in 15 days. Had Shashank left work, 2 days before, the rest work could have been done by Nitish in 18 days. If Shashank reduces his efficiency by 20% and Nitish increase his efficiency by 50%. Then in how many day working together they will finish the work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:1229 days


To solve the problem step by step, we will first determine the efficiencies of Shashank and Nitish based on the information provided, and then calculate how long they will take to complete the work together after adjusting their efficiencies.

Step 1: Determine the work done by Shashank and Nitish
Let Shashank's efficiency be S and Nitish's efficiency be N.

- Shashank works for 12 days, so the work done by him is 12S.
- Nitish completes the remaining work in 15 days, so the work done by him is 15N.

The total work done can be expressed as:
W=12S+15N(1)

Step 2: Analyze the scenario if Shashank left 2 days earlier
If Shashank had left after 10 days, he would have done:
10S
The remaining work would then be done by Nitish in 18 days, so:
Remaining work=18N

Setting the two expressions for the remaining work equal gives us:
12S+15N=10S+18N

Step 3: Simplify the equation
Rearranging the equation:
12S10S=18N15N
2S=3N
From this, we can express S in terms of N:
SN=32(2)

Step 4: Assign values to efficiencies
Let’s assume N=2x (for simplicity), then:
S=3x

Step 5: Calculate total work done
Substituting S and N back into equation (1):
W=12(3x)+15(2x)=36x+30x=66x

Step 6: Adjust efficiencies
Shashank reduces his efficiency by 20%:
New efficiency of Shashank=S=3x0.2(3x)=3x0.6x=2.4x

Nitish increases his efficiency by 50%:
New efficiency of Nitish=N=2x+0.5(2x)=2x+x=3x

Step 7: Calculate combined efficiency
Now, the combined efficiency when they work together is:
Total efficiency=S+N=2.4x+3x=5.4x

Step 8: Calculate time to complete the work together
The total work is 66x. The time taken to complete the work together is:
Time=Total WorkTotal Efficiency=66x5.4x=665.4=12.22 days12 days

Final Answer
Shashank and Nitish will finish the work together in approximately 12.22 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?

    A3/5
    B1/3
    C1/2
    D2/5
  • P is 20% more efficient than Q. If Q alone can finish a work in 10 days, then in how many days will P alone finish the work?

    A813
    B8.5
    C9
    D12
  • A can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.

    A6 days
    B7 days
    C9 days
    D8 days