Shashank started a work and left after 12 days, rest work done by Nitish in 15 days. Had Shashank left work, 2 days before, the rest work could have been done by Nitish in 18 days. If Shashank reduces his efficiency by 20% and Nitish increase his efficiency by 50%. Then in how many day working together they will finish the work?
The correct Answer is:1229 days
To solve the problem step by step, we will first determine the efficiencies of Shashank and Nitish based on the information provided, and then calculate how long they will take to complete the work together after adjusting their efficiencies.
Step 1: Determine the work done by Shashank and Nitish
Let Shashank's efficiency be S and Nitish's efficiency be N.
- Shashank works for 12 days, so the work done by him is 12S.
- Nitish completes the remaining work in 15 days, so the work done by him is 15N.
The total work done can be expressed as:
W=12S+15N(1)
Step 2: Analyze the scenario if Shashank left 2 days earlier
If Shashank had left after 10 days, he would have done:
10S
The remaining work would then be done by Nitish in 18 days, so:
Remaining work=18N
Setting the two expressions for the remaining work equal gives us:
12S+15N=10S+18N
Step 3: Simplify the equation
Rearranging the equation:
12S−10S=18N−15N
2S=3N
From this, we can express S in terms of N:
SN=32(2)
Step 4: Assign values to efficiencies
Let’s assume N=2x (for simplicity), then:
S=3x
Step 5: Calculate total work done
Substituting S and N back into equation (1):
W=12(3x)+15(2x)=36x+30x=66x
Step 6: Adjust efficiencies
Shashank reduces his efficiency by 20%:
New efficiency of Shashank=S′=3x−0.2(3x)=3x−0.6x=2.4x
Nitish increases his efficiency by 50%:
New efficiency of Nitish=N′=2x+0.5(2x)=2x+x=3x
Step 7: Calculate combined efficiency
Now, the combined efficiency when they work together is:
Total efficiency=S′+N′=2.4x+3x=5.4x
Step 8: Calculate time to complete the work together
The total work is 66x. The time taken to complete the work together is:
Time=Total WorkTotal Efficiency=66x5.4x=665.4=12.22 days≈12 days
Final Answer
Shashank and Nitish will finish the work together in approximately 12.22 days.
Let Shashank's efficiency be S and Nitish's efficiency be N.
- Nitish completes the remaining work in 15 days, so the work done by him is 15N.
W=12S+15N(1)
If Shashank had left after 10 days, he would have done:
10S
The remaining work would then be done by Nitish in 18 days, so:
Remaining work=18N
12S+15N=10S+18N
Rearranging the equation:
12S−10S=18N−15N
2S=3N
From this, we can express S in terms of N:
SN=32(2)
Let’s assume N=2x (for simplicity), then:
S=3x
Substituting S and N back into equation (1):
W=12(3x)+15(2x)=36x+30x=66x
Shashank reduces his efficiency by 20%:
New efficiency of Shashank=S′=3x−0.2(3x)=3x−0.6x=2.4x
New efficiency of Nitish=N′=2x+0.5(2x)=2x+x=3x
Now, the combined efficiency when they work together is:
Total efficiency=S′+N′=2.4x+3x=5.4x
The total work is 66x. The time taken to complete the work together is:
Time=Total WorkTotal Efficiency=66x5.4x=665.4=12.22 days≈12 days
Shashank and Nitish will finish the work together in approximately 12.22 days.
Topper's Solved these Questions
Similar Questions
A and B can finish a certain piece of work in 4 days. If A reduces his efficiency by 30% and B increases by 10%, then work will be finished in 5 days. If A works with his original efficiency and B work with 112 times of his efficiency, then in how many days working together work will be finished?
View SolutionA, B and C working together can finish a certain piece of work in 40 days. They work for 25 days and then B left and rest work done by A and C in 20 days. If efficiency of C is half of B's efficiency. Then in how many days A will finish the working alone?
View Solution
Knowledge Check
Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?
A3/5B1/3C1/2D2/5P is 20% more efficient than Q. If Q alone can finish a work in 10 days, then in how many days will P alone finish the work?
A813B8.5C9D12A can do a work in 12 days and B can do it in 16 days. A and B started the work jointly and A left 2 days before the work is finished. Find the number of days they took to finish the work.
A6 daysB7 daysC9 daysD8 days
A, B and C working together can finish a piece of work in 32 days. They worked for 24 days and after that the C left. Rest of the work is completed by A and B in 28 days. Work done by A in 1 day is equal to work done by B in 2 days. In how many days working alone each one will finish the work?
View SolutionS can finish 50% of a work in a day. T can do 25% of the work in a day. Both of them together will finish the work in...days.
View SolutionA, B and C working together can finish certain piece of work in 28 days. They work together for 18 days, then B left. If rest work done by A and C in 25 days. Work done by A in 2 days is equal to work done by C in 3 days, then find in how many days A, B and C working alone will finish the work?
View SolutionA can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View SolutionA can do a piece of work in 48 days. If B is 50% more efficient than A, then in how many days can B do the same work?
View Solution