Doubtnut Promotions Sticky

A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished 11 days Earlier. How many persons were there when the work started?

A

1. 17

B

2. 24

C

3. 30

D

4. 22

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step-by-step, let's denote the number of persons initially as x.

Step 1: Understand the work done
The problem states that a certain number of persons can complete the work in 55 days. This means that the total work can be expressed in terms of person-days. The total work W can be calculated as:
W=x×55

Step 2: Work done with additional persons
If there were 6 more persons, the number of persons becomes x+6. The work can then be completed in 11 days earlier, which means it can be completed in:
5511=44 days
Thus, the total work can also be expressed as:
W=(x+6)×44

Step 3: Set up the equation
Since both expressions represent the same total work W, we can set them equal to each other:
x×55=(x+6)×44

Step 4: Expand and simplify the equation
Expanding the right side of the equation gives:
55x=44x+264
Now, we can isolate x by moving 44x to the left side:
55x44x=264
This simplifies to:
11x=264

Step 5: Solve for x
Now, divide both sides by 11 to find x:
x=26411=24

Conclusion
Thus, the number of persons when the work started was 24.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?

    A17
    B24
    C30
    D22
  • Question 2 - Select One

    a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?

    A17
    B24
    C30
    D22
  • Question 3 - Select One

    A certain number of men com plete a piece of work in 60 days. If there were 8 men more, the work can be finished in 10 days less. The number of men originally is:

    A30
    B40
    C32
    D36