If 4 men working 4 hours per day for 4 days complete 4.units of work, then how many units of work will be completed by 2 men working for 2 hours per day in 2 days ?
2
1
12
18
To solve the problem step by step, we can use the concept of work done, which can be calculated using the formula:
Work=Number of Men×Hours per Day×Number of Days
Step 1: Calculate the total work done by the first group of men
Given:
- Number of men (m1) = 4
- Hours per day (h1) = 4
- Number of days (d1) = 4
Using the formula:
Total Work=m1×h1×d1
Substituting the values:
Total Work=4×4×4=64 man-hours
Step 2: Determine the work done per unit of work
We know that 4 units of work are completed by 64 man-hours. Therefore, the work done per unit is:
Work per unit=Total WorkUnits of Work=64 man-hours4 units=16 man-hours per unit
Step 3: Calculate the total work done by the second group of men
Now we need to find out how much work 2 men can do in 2 hours per day for 2 days.
Given:
- Number of men (m2) = 2
- Hours per day (h2) = 2
- Number of days (d2) = 2
Using the formula again:
Total Work by 2 men=m2×h2×d2=2×2×2=8 man-hours
Step 4: Calculate the units of work completed by the second group
Now, we can find out how many units of work this corresponds to:
Units of Work=Total Work by 2 menWork per unit=8 man-hours16 man-hours per unit=0.5 units
Final Answer
Thus, the number of units of work completed by 2 men working for 2 hours per day in 2 days is 0.5 units.
---
- Number of men (m1) = 4
- Hours per day (h1) = 4
- Number of days (d1) = 4
- Number of men (m2) = 2
- Hours per day (h2) = 2
- Number of days (d2) = 2
Similar Questions
On working 10 hourse a day, 15 men can complete a piece of work in 20 days. In how many days can 30 men complete if they work 5 hours per day?
View Solution10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution
Knowledge Check
If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for n days is
Ap2n2Bp3n2Cn2p2Dn3p2If 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?
A30 daysB20 daysC60 daysD40 daysIf 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?A50B60C54D45
If 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212
View SolutionIf 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?
यदि 16 पुरुष प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 27 दिनों में पूरा करते हैं, तो इस कार्य को 24 दिनों में पूरा करने के लिए 18 पुरुषों को दिन में कितने घंटे कार्य करना पड़ेगा ?
View SolutionIf 10 men finish 10 unit work in 10 days at 10 hours per day, then how many units of work will 5 men complete in 5 days at 5 hours per day ?
View Solution24 persons working 8 hours a day can complete 2 units of a work in 10 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
एक दिन में 8 घंटे कार्य करते हुए 24 व्यक्ति किसी कार्य की 2 इकाई 10 दिनों में समाप्त कर सकते हैं | इस कार्य की 4 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी यदि वे 16 दिनों तक एक दिन में 6 घंटे कार्य करते हैं ?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution