If 4 men working 4 hours per day for 4 days complete 4.units of work, then how many units of work will be completed by 2 men working for 2 hours per day in 2 days ?

A

2

B

1

C

12

D

18

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we can use the concept of work done, which can be calculated using the formula:

Work=Number of Men×Hours per Day×Number of Days

Step 1: Calculate the total work done by the first group of men

Given:
- Number of men (m1) = 4
- Hours per day (h1) = 4
- Number of days (d1) = 4

Using the formula:

Total Work=m1×h1×d1

Substituting the values:

Total Work=4×4×4=64 man-hours

Step 2: Determine the work done per unit of work

We know that 4 units of work are completed by 64 man-hours. Therefore, the work done per unit is:

Work per unit=Total WorkUnits of Work=64 man-hours4 units=16 man-hours per unit

Step 3: Calculate the total work done by the second group of men

Now we need to find out how much work 2 men can do in 2 hours per day for 2 days.

Given:
- Number of men (m2) = 2
- Hours per day (h2) = 2
- Number of days (d2) = 2

Using the formula again:

Total Work by 2 men=m2×h2×d2=2×2×2=8 man-hours

Step 4: Calculate the units of work completed by the second group

Now, we can find out how many units of work this corresponds to:

Units of Work=Total Work by 2 menWork per unit=8 man-hours16 man-hours per unit=0.5 units

Final Answer

Thus, the number of units of work completed by 2 men working for 2 hours per day in 2 days is 0.5 units.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for n days is

    Ap2n2
    Bp3n2
    Cn2p2
    Dn3p2
  • If 10 men working for 6 hours per day can complete a piece of work in 90 days, in how many days will 6 men working for 15 hours per day complete the same piece of work ?

    A30 days
    B20 days
    C60 days
    D40 days
  • If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
    यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?

    A50
    B60
    C54
    D45