Doubtnut Promotions Sticky

18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?

A

25

B

15

C

20

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will first determine the total work done in terms of person-hours and then use that information to find out how many persons are required to complete the new task.

Step 1: Calculate the total work done in person-hours for the first scenario.

Given:
- 18 persons
- 8 hours a day
- 10 days
- 3 units of work

Total work done in person-hours can be calculated as:
Total Work=Number of Persons×Hours per Day×Number of Days
Total Work=18×8×10=1440 person-hours

This means that 1440 person-hours are required to complete 3 units of work.

Step 2: Calculate the work done per unit.

To find the work done per unit, we divide the total work by the number of units:
Work per Unit=Total WorkUnits of Work=14403=480 person-hours per unit

Step 3: Calculate the total work required for the new scenario.

Now, we need to find out how much work is required to complete 5 units of work:
Total Work for 5 Units=5×480=2400 person-hours

Step 4: Calculate the total available work hours in the new scenario.

In the new scenario, we have:
- Working hours per day = 6 hours
- Number of days = 16 days

The total available work hours can be calculated as:
Total Available Work Hours=Hours per Day×Number of Days=6×16=96 hours

Step 5: Calculate the number of persons required.

Let x be the number of persons required. The total work done by x persons in 96 hours should equal the total work required for 5 units:
x×96=2400
Now, solving for x:
x=240096=25

Conclusion:

Thus, the number of persons required to complete 5 units of work in 16 days working 6 hours a day is 25.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    24 persons working 8 hours a day can complete 2 units of a work in 10 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
    एक दिन में 8 घंटे कार्य करते हुए 24 व्यक्ति किसी कार्य की 2 इकाई 10 दिनों में समाप्त कर सकते हैं | इस कार्य की 4 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी यदि वे 16 दिनों तक एक दिन में 6 घंटे कार्य करते हैं ?

    A48
    B36
    C40
    D32
  • Question 2 - Select One

    36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?

    A50
    B55
    C60
    D45
  • Question 3 - Select One

    36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?
    प्रतिदिन 8 घंटे कार्य करके 36 लोग किसी कार्य की 3 इकाई 12 दिनों में कर सकते हैं| यदि वे एक दिन में 6 घंटे कार्य करें तो 16 दिन में इस कार्य की 5 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी ?

    A50
    B55
    C60
    D45