Doubtnut Promotions Sticky

A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is

A

100

B

96

C

95

D

90

Video Solution
Text Solution
Verified by Experts

The correct Answer is:B


माना कि B तथा C कार्य को पूरा करने के लिए x दिन लेते हैं।
A द्वारा लिया गया समय = 3xदिन
प्रश्नानुसार
1x+13x=124
43x=124
x=32 अतः A को कार्य पूरा करने में 3×32=96दिन लगेंगे।

|
Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    X works four times as fast as Y.Y takes 60 days more than X to complete a job. Find the time in which X and Y working together can complete the job ( in days)

    A20
    B10
    C16
    D12
  • Question 2 - Select One

    To do a certain work, B would take time thrice as long as A and C together and C twice as long as A and B together. The three men together complete the work in 10 days. The time taken by A to complete the work separately is

    A22 days
    B24 days
    C30 days
    D20 days
  • Question 3 - Select One

    A and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in

    A12 days
    B14 days
    C16 days
    D24 days