A can complete 3313% of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:
712 days
5 days
7 days
512 days
The correct Answer is:C
To solve the problem step by step, let's break it down:
Step 1: Determine the total work
A can complete 3313% of the work in 5 days.
First, convert 3313% to a fraction:
3313%=1003%
This means A completes 1003÷100=13 of the work in 5 days.
To find the total work, we can set up the equation:
Total Work=5 days×3=15 days
Thus, the total work can be considered as 15 units.
Step 2: Determine B's work rate
B can complete 40% of the work in 10 days.
Convert 40% to a fraction:
40%=40100=25
This means B completes 25 of the work in 10 days.
To find the total work, we can set up the equation:
Total Work=10 days×52=25 days
Thus, the total work can be considered as 25 units.
Step 3: Find the LCM of work rates
Now, we need to find the least common multiple (LCM) of the days taken by A and B to complete the work:
- A takes 15 days to complete the work.
- B takes 25 days to complete the work.
The LCM of 15 and 25 is 75 days.
Step 4: Calculate work done by A and B in one day
Now, let's find the work done by A and B in one day:
- A's work rate = 115 of the work per day.
- B's work rate = 125 of the work per day.
Step 5: Work done by A and B together in one day
The combined work done by A and B in one day:
Work done by A + Work done by B=115+125
To add these fractions, find a common denominator (which is 75):
115=575,125=375
Thus,
Combined work=575+375=875
Step 6: Work done in 5 days
In 5 days, the total work done by A and B together:
Total work in 5 days=5×875=4075=815
Step 7: Remaining work
Now, we need to find the remaining work after 5 days:
Remaining work=1−815=15−815=715
Step 8: Time taken by A to complete remaining work
Now, we need to find out how long A will take to complete the remaining work:
A's work rate is 115 of the work per day. To find the time taken to complete 715 of the work:
Time=Remaining workA's work rate=715115=7 days
Final Answer
A alone will complete the remaining work in 7 days.
---
A can complete 3313% of the work in 5 days.
3313%=1003%
This means A completes 1003÷100=13 of the work in 5 days.
Total Work=5 days×3=15 days
Thus, the total work can be considered as 15 units.
B can complete 40% of the work in 10 days.
40%=40100=25
This means B completes 25 of the work in 10 days.
Total Work=10 days×52=25 days
Thus, the total work can be considered as 25 units.
Now, we need to find the least common multiple (LCM) of the days taken by A and B to complete the work:
- A takes 15 days to complete the work.
- B takes 25 days to complete the work.
Now, let's find the work done by A and B in one day:
- A's work rate = 115 of the work per day.
- B's work rate = 125 of the work per day.
The combined work done by A and B in one day:
Work done by A + Work done by B=115+125
To add these fractions, find a common denominator (which is 75):
115=575,125=375
Thus,
Combined work=575+375=875
In 5 days, the total work done by A and B together:
Total work in 5 days=5×875=4075=815
Now, we need to find the remaining work after 5 days:
Remaining work=1−815=15−815=715
Now, we need to find out how long A will take to complete the remaining work:
A's work rate is 115 of the work per day. To find the time taken to complete 715 of the work:
Time=Remaining workA's work rate=715115=7 days
A alone will complete the remaining work in 7 days.
Similar Questions
A can complete one-third of a work in 5 days and B can complete 40% of the work in 10 days. In how many days both A and B together can complete the work?
View SolutionA can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?
View Solution
Knowledge Check
- Question 1 - Select One
A can do 35th of a work in 12 days, B can do 13rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?
A9 daysB6 daysC4 daysD5 days - Question 2 - Select One
A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
A6 daysB4 daysC8 daysD9 days - Question 3 - Select One
A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
A6B214C812D9
A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A alone can complete the work in
View SolutionA can complete a piece of work in 6 days while B can complete the same work in 12 days. If they work together and complete it then, the portion of the work done by A is
View SolutionA can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
View SolutionA and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View SolutionP can complete 13 of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes 13 of the work in 13 days and S, 16 of the work in 7 days. Who will be able to complete the work first?
View Solution