Doubtnut Promotions Sticky

A can complete 3313% of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:

A

712 days

B

5 days

C

7 days

D

512 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break it down:

Step 1: Determine the total work
A can complete 3313% of the work in 5 days.

First, convert 3313% to a fraction:
3313%=1003%
This means A completes 1003÷100=13 of the work in 5 days.

To find the total work, we can set up the equation:
Total Work=5 days×3=15 days
Thus, the total work can be considered as 15 units.

Step 2: Determine B's work rate
B can complete 40% of the work in 10 days.

Convert 40% to a fraction:
40%=40100=25
This means B completes 25 of the work in 10 days.

To find the total work, we can set up the equation:
Total Work=10 days×52=25 days
Thus, the total work can be considered as 25 units.

Step 3: Find the LCM of work rates
Now, we need to find the least common multiple (LCM) of the days taken by A and B to complete the work:
- A takes 15 days to complete the work.
- B takes 25 days to complete the work.

The LCM of 15 and 25 is 75 days.

Step 4: Calculate work done by A and B in one day
Now, let's find the work done by A and B in one day:
- A's work rate = 115 of the work per day.
- B's work rate = 125 of the work per day.

Step 5: Work done by A and B together in one day
The combined work done by A and B in one day:
Work done by A + Work done by B=115+125
To add these fractions, find a common denominator (which is 75):
115=575,125=375
Thus,
Combined work=575+375=875

Step 6: Work done in 5 days
In 5 days, the total work done by A and B together:
Total work in 5 days=5×875=4075=815

Step 7: Remaining work
Now, we need to find the remaining work after 5 days:
Remaining work=1815=15815=715

Step 8: Time taken by A to complete remaining work
Now, we need to find out how long A will take to complete the remaining work:
A's work rate is 115 of the work per day. To find the time taken to complete 715 of the work:
Time=Remaining workA's work rate=715115=7 days

Final Answer
A alone will complete the remaining work in 7 days.

---

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do 35th of a work in 12 days, B can do 13rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?

    A9 days
    B6 days
    C4 days
    D5 days
  • Question 2 - Select One

    A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days
  • Question 3 - Select One

    A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

    A6
    B214
    C812
    D9