Doubtnut Promotions Sticky

P can complete 13 of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes 13 of the work in 13 days and S, 16 of the work in 7 days. Who will be able to complete the work first?

A

P

B

Q

C

R

D

S

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To determine who will complete the work first among P, Q, R, and S, we need to find out how long each person takes to complete the entire work.

1. Calculate the total time taken by P to complete the work:
- P can complete 13 of the work in 10 days.
- To find the time taken to complete the entire work (1 unit), we set up the proportion:
Time taken by P=10 days×31=30 days

2. Calculate the total time taken by Q to complete the work:
- Q can complete 40% of the work in 15 days.
- 40% can be expressed as 40100=25.
- To find the time taken to complete the entire work:
Time taken by Q=15 days×52=37.5 days

3. Calculate the total time taken by R to complete the work:
- R can complete 13 of the work in 13 days.
- To find the time taken to complete the entire work:
Time taken by R=13 days×31=39 days

4. Calculate the total time taken by S to complete the work:
- S can complete 16 of the work in 7 days.
- To find the time taken to complete the entire work:
Time taken by S=7 days×61=42 days

5. Compare the total times taken by each worker:
- P: 30 days
- Q: 37.5 days
- R: 39 days
- S: 42 days

6. Determine who completes the work first:
- The worker who takes the least amount of time is P, who takes 30 days.

Conclusion:
P will be able to complete the work first in 30 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P can complete 13 of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes 13 of the work in 13 days and S, 16 of the work in 7 days. Who will be able to complete the work first?

    AP
    BQ
    CR
    DS
  • Question 2 - Select One

    X can do 14 of a work in 10 days, Y can do 40% of the same work in 40 days and Z can do 13 of the work in 13 days. Who will complete the work first?

    AX
    BY
    CZ
    Dboth X and Z
  • Question 3 - Select One

    A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

    A6
    B214
    C812
    D9