P can complete 13 of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes 13 of the work in 13 days and S, 16 of the work in 7 days. Who will be able to complete the work first?
P
Q
R
S
The correct Answer is:B
To determine who will complete the work first among P, Q, R, and S, we need to find out how long each person takes to complete the entire work.
1. Calculate the total time taken by P to complete the work:
- P can complete 13 of the work in 10 days.
- To find the time taken to complete the entire work (1 unit), we set up the proportion:
Time taken by P=10 days×31=30 days
2. Calculate the total time taken by Q to complete the work:
- Q can complete 40% of the work in 15 days.
- 40% can be expressed as 40100=25.
- To find the time taken to complete the entire work:
Time taken by Q=15 days×52=37.5 days
3. Calculate the total time taken by R to complete the work:
- R can complete 13 of the work in 13 days.
- To find the time taken to complete the entire work:
Time taken by R=13 days×31=39 days
4. Calculate the total time taken by S to complete the work:
- S can complete 16 of the work in 7 days.
- To find the time taken to complete the entire work:
Time taken by S=7 days×61=42 days
5. Compare the total times taken by each worker:
- P: 30 days
- Q: 37.5 days
- R: 39 days
- S: 42 days
6. Determine who completes the work first:
- The worker who takes the least amount of time is P, who takes 30 days.
Conclusion:
P will be able to complete the work first in 30 days.
- P can complete 13 of the work in 10 days.
- To find the time taken to complete the entire work (1 unit), we set up the proportion:
Time taken by P=10 days×31=30 days
- Q can complete 40% of the work in 15 days.
- 40% can be expressed as 40100=25.
- To find the time taken to complete the entire work:
Time taken by Q=15 days×52=37.5 days
- R can complete 13 of the work in 13 days.
- To find the time taken to complete the entire work:
Time taken by R=13 days×31=39 days
- S can complete 16 of the work in 7 days.
- To find the time taken to complete the entire work:
Time taken by S=7 days×61=42 days
- P: 30 days
- Q: 37.5 days
- R: 39 days
- S: 42 days
- The worker who takes the least amount of time is P, who takes 30 days.
P will be able to complete the work first in 30 days.
Topper's Solved these Questions
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOURSELF25videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - TYPE-V19videos
TIME AND WORK
- BOOK - KIRAN PUBLICATIONCHAPTER - TIME AND DISTANCEEXERCISE - Type -XI74videos
TIME AND DISTANCE
- BOOK - KIRAN PUBLICATIONCHAPTER - TRIGONOMETRY EXERCISE - TEST YOURSELF25videos
TRIGONOMETRY
Similar Questions
X can do 14 of a work in 10 days, Y can do 40% of the work in 40 days and Z can do 13 of the work in 13 days. Who will complete the work first? a. X b. Y c. Z d. XandZ both
View SolutionIf man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?
View Solution
Knowledge Check
- Question 1 - Select One
P can complete 13 of a work in 10 days, Q can complete 40% of the same work in 15 days, R, completes 13 of the work in 13 days and S, 16 of the work in 7 days. Who will be able to complete the work first?
APBQCRDS - Question 2 - Select One
X can do 14 of a work in 10 days, Y can do 40% of the same work in 40 days and Z can do 13 of the work in 13 days. Who will complete the work first?
AXBYCZDboth X and Z - Question 3 - Select One
A can complete of a work in 8 days. B can complete35 of the same work in 12 days and C can complete 49 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?
A6B214C812D9
A can complete 3313% of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:
View SolutionP can do (1/4)th of work in 10 days, Q can do 40% of work in 40 days and R can do (1/3)rd of work in 13 days. Who will complete the work first?
View SolutionA can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?
View SolutionX and Y can complete a work in 5 days. Y and Z can complete the same work in 6 days. Z and X can complete the same work in 152 days. In how many days will X, Y and Z together complete the work?
View SolutionIf A can complete work in 6 days, B can complete the work in 8 days and C can complete the same work in 12 days. In how much time A, B, and C can complete the work.
View Solution