A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:

A

8 days

B

5 days

C

4 days

D

6 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step-by-step, we will break down the information provided and calculate the required values.

Step 1: Calculate the total work done by A and B
- A can do 45 of the work in 20 days.
- Therefore, A can complete the entire work in 20 days45=25 days.
- This means A's work rate is 125 of the work per day.

- B can do 34 of the work in 15 days.
- Therefore, B can complete the entire work in 15 days34=20 days.
- This means B's work rate is 120 of the work per day.

Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B is:
Work rate of A+Work rate of B=125+120
- To add these fractions, we find a common denominator, which is 100:
125=4100,120=5100
- Therefore,
Combined work rate=4100+5100=9100

Step 3: Calculate the work done by A and B in 10 days
- In 10 days, A and B together can complete:
10×9100=90100=0.9 (or 90% of the work)

Step 4: Calculate the remaining work
- Since A and B completed 90% of the work, the remaining work is:
10.9=0.1 (or 10% of the work)

Step 5: Determine the work done by C
- C completes the remaining 10% of the work in 1 day. Therefore, C's work rate is:
C's work rate=0.1 work per day
- This means C can complete the entire work in 10.1=10 days.

Step 6: Calculate the combined work rate of B and C
- B's work rate is 120 and C's work rate is 0.1.
- To find the combined work rate of B and C:
Work rate of B+Work rate of C=120+0.1
- Converting 0.1 to a fraction gives us 110:
120+110=120+220=320

Step 7: Calculate the time taken by B and C to complete 34 of the work
- To find out how long it takes for B and C to complete 34 of the work:
Time=WorkCombined work rate=34320=34×203=5 days

Final Answer
B and C together can complete 34 of the work in 5 days.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days
  • A can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :

    A212 days
    B3 days
    C112 days
    D2 days
  • A can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

    A12 days
    B9 days
    C10 days
    D8 days