A can do 45 of a work in 20 days and B can do 34 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 34 of the same work in:
8 days
5 days
4 days
6 days
The correct Answer is:B
To solve the problem step-by-step, we will break down the information provided and calculate the required values.
Step 1: Calculate the total work done by A and B
- A can do 45 of the work in 20 days.
- Therefore, A can complete the entire work in 20 days45=25 days.
- This means A's work rate is 125 of the work per day.
- B can do 34 of the work in 15 days.
- Therefore, B can complete the entire work in 15 days34=20 days.
- This means B's work rate is 120 of the work per day.
Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B is:
Work rate of A+Work rate of B=125+120
- To add these fractions, we find a common denominator, which is 100:
125=4100,120=5100
- Therefore,
Combined work rate=4100+5100=9100
Step 3: Calculate the work done by A and B in 10 days
- In 10 days, A and B together can complete:
10×9100=90100=0.9 (or 90% of the work)
Step 4: Calculate the remaining work
- Since A and B completed 90% of the work, the remaining work is:
1−0.9=0.1 (or 10% of the work)
Step 5: Determine the work done by C
- C completes the remaining 10% of the work in 1 day. Therefore, C's work rate is:
C's work rate=0.1 work per day
- This means C can complete the entire work in 10.1=10 days.
Step 6: Calculate the combined work rate of B and C
- B's work rate is 120 and C's work rate is 0.1.
- To find the combined work rate of B and C:
Work rate of B+Work rate of C=120+0.1
- Converting 0.1 to a fraction gives us 110:
120+110=120+220=320
Step 7: Calculate the time taken by B and C to complete 34 of the work
- To find out how long it takes for B and C to complete 34 of the work:
Time=WorkCombined work rate=34320=34×203=5 days
Final Answer
B and C together can complete 34 of the work in 5 days.
- A can do 45 of the work in 20 days.
- Therefore, A can complete the entire work in 20 days45=25 days.
- This means A's work rate is 125 of the work per day.
- Therefore, B can complete the entire work in 15 days34=20 days.
- This means B's work rate is 120 of the work per day.
- The combined work rate of A and B is:
Work rate of A+Work rate of B=125+120
- To add these fractions, we find a common denominator, which is 100:
125=4100,120=5100
- Therefore,
Combined work rate=4100+5100=9100
- In 10 days, A and B together can complete:
10×9100=90100=0.9 (or 90% of the work)
- Since A and B completed 90% of the work, the remaining work is:
1−0.9=0.1 (or 10% of the work)
- C completes the remaining 10% of the work in 1 day. Therefore, C's work rate is:
C's work rate=0.1 work per day
- This means C can complete the entire work in 10.1=10 days.
- B's work rate is 120 and C's work rate is 0.1.
- To find the combined work rate of B and C:
Work rate of B+Work rate of C=120+0.1
- Converting 0.1 to a fraction gives us 110:
120+110=120+220=320
- To find out how long it takes for B and C to complete 34 of the work:
Time=WorkCombined work rate=34320=34×203=5 days
B and C together can complete 34 of the work in 5 days.
Similar Questions
A can do a work in 4 days while B can do that same work in 6 days. If they worked together, then that work would be completed in
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution
Knowledge Check
A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
A6 daysB4 daysC8 daysD9 daysA can do 40% of a work in 12 days, whereas B can do 60% of the same work in 15 days. Both work together for 10 days. C completes the remaining work alone in 4 days. A, B and C together will complete 28% of the same work in :
A212 daysB3 daysC112 daysD2 daysA can do 25 of a work in 6 days and B can do 23 of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:
A12 daysB9 daysC10 daysD8 days
A can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:
View SolutionA can do 35th of a work in 12 days, B can do 13rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?
View SolutionA can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
View SolutionA can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
View SolutionA and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
View Solution