If A, B and C can do a piece of work in 5 days, B, C and D can do the same work in 10 days, C, D, and A can do the same work in 15 days, D, A and B can do the same work in 30 days. Find the time taken by A+B+C+D ?

A

A)9 days

B

B)7 days

C

C)9.5 days

D

D)7.5 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem, we need to determine the individual efficiencies of A, B, C, and D based on the information provided. Let's break it down step by step.

Step 1: Determine the total work done
We know that:
- A, B, and C can complete the work in 5 days.
- B, C, and D can complete the work in 10 days.
- C, D, and A can complete the work in 15 days.
- D, A, and B can complete the work in 30 days.

To make calculations easier, we can assume the total work is 60 units (the least common multiple of the days).

Step 2: Calculate the efficiencies
1. Efficiency of A, B, and C:
Work done by A, B, C in 5 days=60 units
Daily work=605=12 units
So, A+B+C=12.

2. Efficiency of B, C, and D:
Work done by B, C, D in 10 days=60 units
Daily work=6010=6 units
So, B+C+D=6.

3. Efficiency of C, D, and A:
Work done by C, D, A in 15 days=60 units
Daily work=6015=4 units
So, C+D+A=4.

4. Efficiency of D, A, and B:
Work done by D, A, B in 30 days=60 units
Daily work=6030=2 units
So, D+A+B=2.

Step 3: Set up equations
Now we have the following equations:
1. A+B+C=12 (1)
2. B+C+D=6 (2)
3. C+D+A=4 (3)
4. D+A+B=2 (4)

Step 4: Solve the equations
We can add all four equations together:
(A+B+C)+(B+C+D)+(C+D+A)+(D+A+B)=12+6+4+2
This simplifies to:
3A+3B+3C+3D=24
Dividing the entire equation by 3 gives:
A+B+C+D=8

Step 5: Calculate the time taken by A + B + C + D
Since A+B+C+D=8 units of work can be done in one day, we can find the number of days required to complete the total work of 60 units:
Time taken=Total WorkDaily Work=608=7.5 days

Final Answer
The time taken by A + B + C + D to complete the work is 7.5 days.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is

    A5 days
    B10 days
    C15 days
    D20 days
  • Question 2 - Select One

    A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

    A4 days
    B9 days
    C8 days
    D5 days
  • Question 3 - Select One

    A and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A and C complete it in 8 days. In how many days A, B and C can complete the whole work, working together?

    A8
    B10
    C12
    D16